Top

Top

 

Agenda Item No

 

The Vale of Glamorgan Council

 

Scrutiny Committee (Lifelong Learning) 23rd January 2012

 

Report of the Director of Learning and Development

 

Revenue and Capital Monitoring for the period 1st April 2011 to 30th November 2011

 

Purpose of the Report

1.             To bring to the attention of this Scrutiny Committee, the position in respect of revenue and capital expenditure for the period 1st April 2011 to 30th November 2011 regarding those revenue and capital budgets, which form this Committee’s remit

Recommendation

1.             It is recommended that the Scrutiny Committee note the position with regard to the 2011/12 revenue and capital monitoring.

Reason for the Recommendation

1.             That Members are aware of the position with regard to the 2011/12 revenue and capital monitoring relevant to this Scrutiny Committee.

Background

2.             On 16th November 2011, Cabinet approved the amended revenue budget for 2011/12 (min no c1511).  Reports monitoring expenditure are brought to this Committee on a regular basis.

Relevant Issues and Options

3.             The Revenue Budget and projected outturn for 2011/2012 are shown in Appendix 1.

4.             Education - Overall, the Education Budget is currently projected to overspend by £66,000 at year end, however it will be funded from Education Reserves.  This overspend is due to a projected £82,000 overspend against the Additional Learning Needs (ALN) budget offset by a £16,000 underspend against School Improvement due to increased income generated in year.

5.             The ALN overspend is made up of a projected overspend of £220k for LSA support, also additional Independent schools expenditure has been incurred in year of £122k. As part of the efficiency savings implemented for 2011/12 and 2012/13 £56k has been incurred for redundancies in year. These overspends have also been offset by increased Recoupment Income and reduced Recoupment Expenditure of £232k, a £42k saving has been found from a vacant post in Primary Behaviour Support Team and a £25k underspend against the Secondary Behaviour Support budget has been identified. The balance of £17k has been found from additional grant income and early implementation of 12/13 savings.  The ALN budget is a volatile budget that is demand led, the position will be monitored closely throughout the year. It is possible that the projected overspend may reduce due to increased recoupment income or reduced out of county expenditure.

6.             In addition, there is a projected overspend of £54k on Mainstream Education Transport, shown against Environmental and Economic Regeneration Services, who manage the budget.  This overspend will be met by the use of Education Reserves and has been reflected in Appendix 1.

7.             Provision has been made within the budget for the annual cost of financing the School Investment Strategy of £600,000. This sum will be transferred to the School Investment Strategy Reserve.

8.             In addition, to finance the Schools' contributions to the Early Retirement / Voluntary Redundancy scheme, Education is projecting to transfer £316,000 from Education Reserves.  This will be repaid by participating schools over 2012/13 and 2013/14.

9.             Schools - The delegated budget relating to schools is expected to balance as any under/over spend is carried forward by schools.

10.        Libraries - This service has a favourable variance of £21k and is currently anticipated to outturn within budget.

11.        Lifelong Learning - This service has a favourable variance of £16k and is currently anticipated to outturn within budget, using projected favourable variances within both the Lifelong Learning Employment and Training Service section and the Communities First Management fees.  This will offset a projected £55k adverse variance within Community Enterprise, resulting from delays in implementing 2011/12 savings.

12.        Catering - This service has a favourable variance of £9k and is currently anticipated to outturn within budget.  However the service can be affected by external factors and the requirement to meet WG nutritional guidelines.  The budget will continue to be closely monitored and any variations will be reported to future meetings.

Capital Programme 2011/12

13.        Appendix 2 details financial progress on the Capital Programme as at 30th November 2011.

14.        For all schemes where it is evident that the full year's budget will not be spent during the year, the relevant officers will be required to provide an explanation for the shortfall and this shall be taken to earliest available Cabinet.

15.        Welsh Medium School, Llantwit Major - This scheme is projected to exceed its budget by some £58,000. This is due to several factors, such as additional ground works and furniture, fittings and equipment costs. It is proposed that this sum will be funded from the School Investment Strategy reserve. A separate report will be presented to Cabinet to outline progress on this and the Barry Welsh Medium School project.

16.        Pendoylan Church in Wales Primary School - The Authority has agreed a total contribution of £388,000 to the school's remodelling works. The sum of £288,000 has been approved for 2011/12 whilst a further £100,000 has been programmed for 2012/13. Delays on site at the school however have meant that the profiled expenditure for this financial year will fall slightly short of the £288,000. As such it has been requested that the sum of £33,000 be slipped into 2012/13 in order to complete the contribution.  This will require Council approval.

17.        Appendix 3 provides non-financial information on capital schemes with a budget of over £100,000.   Where a budget shown in Appendix 2 is more than £100,000 but is made up of several schemes that individually are less than £100,000, the scheme is not included in Appendix 3.

Resource Implications (Financial and Employment and Climate Change if appropriate)

18.        As detailed in the body of the report.

Legal Implications (to Include Human Rights Implications)

19.        None.

Crime and Disorder Implications

20.        None.

Equal Opportunities Implications (to include Welsh Language issues)

21.        There are no equal opportunity implications.

Corporate/Service Objectives

22.        Effective monitoring assists in the provision of accurate and timely information to officers and Members and in particular allows services to better manage their resources.

Policy Framework and Budget

23.        The report is in accordance with the Policy Framework and Budget.

Consultation (including Ward Member Consultation)

24.        The appropriate Chief Officer has been consulted. This report does not require Ward Member consultation.

Background Papers

None.

Contact Officer

Carolyn Michael (Senior Group Accountant) (01446 709778)

Officers Consulted

Director of Learning and Development

Responsible Officer:

Bryan Jeffreys, Director of Learning and Development

 

Share on facebook Like us on Facebook