SCRUTINY COMMITTEE (CORPORATE RESOURCES)
MINUTES of a meeting held on 20th February, 2007.
Present: Councillor H.J.W. James (Chairman); Councillor Mrs.
C.V.L. Clay (Vice-Chairman); Councillors Ms. L. Burnett, Mrs. J.E.
Charles, Miss. J. Cole, M.R. Harvey, N.P. Hodges, T.H. Jarvie, F.T.
Johnson, Mrs. M. Kelly Owen, C.L. Osborne, A.G. Powell, B.I. Shaw
and K.R. Stockdale.
Also present: Councillor Mrs. M. Randall.
846 APOLOGIES FOR ABSENCE-
These were received from Councillors A D Dobbinson and M R
Wilson.
847 MINUTES-
RESOLVED -THAT the minutes of the meeting held on 23 January
2007 be approved as a correct record.
848 DECLARATIONS OF INTEREST-
There were no declarations received.
849 SOCIAL SERVICE ISSUES (CX) -
Committee were updated on current arrangements with Social
Services as a result of the Chairman having raised a number of
concerns, i.e.
Lack of corporate governance, process and controls for proper
management of the budget of the department.
Action to tackle on-going re-organisation required to deliver
good service at affordable cost.
Staffing and future resourcing issues for the proper delivery of
a well managed department.
The impact of the overall Council’s operations of the
re-organisation.
Change management within the department as a whole.
Ongoing financial and budget viability of the Council
Consultation and involvement of key partners such as WAG, SSIA,
Vale LHB, and the voluntary sector.
To assist members in their deliberations, copies of the report
submitted to Cabinet on 21 December 2006 had been circulated. The
report had provided a background to consideration of the Chairman’s
concerns as did the report to Scrutiny Committee (Community
Wellbeing and Safety) of the 12 February 2007.
In addition, members of the Committee received a copy of the
most to up-to-date version of the Change Plan.
Members were advised that work was underway to link the Change
Plan with the Service Plan and the Council’s response to the Joint
Review in order that everyone would be working from one single
document.
The Chairman acknowledged that most of the points that he had
raised were more than adequately dealt with in the Change Plan but
enquired as to the completion date and resource implications.
The Committee were advised that, whilst the Council had approved
a three year budget to bring spending back to base level, work on
the detail was currently in progress and it could be seen from the
Change Plan that much of the work was classified as being of high
priority.
Much of the work of the Improvement and Development Team this
year would be dedicated to assisting in the preparation and
implementation of the Change Plan. There would inevitably be an
impact on their scheduled work programme, but it was crucial that
the timescale set as part of the budget strategy be maintained.
The following question and answer session then ensued:
| Question |
Answer |
| Regarding the
action “introduce effective system for first contact and referral”,
will a child access the system at the right point? |
This is crucial. Business Process Re-engineering will be
used to consider this point. Good social work requires good
business systems and support. |
| Regarding the proposed review of Out of
County placements – is this feasible? |
There are a range of pressures on this area of service i.e.
parental choice/court choice. Underpinning these issues is the fact
that children do better the closer they are to home.
The answer to the question is that the review is feasible but
assumptions should not be made at this stage.
|
| The Change Plan is a management process. Are
officers satisfied that the document will meet the budget
requirements? |
The Change Plan represents “work in progress”. A
significant element will be the engagement of Managers. The
impression of the Interim Manager of Social Services was that the
staff would rise to the challenge. |
| Cultural change is one of the greatest
challenges. Does the Council have the required levels of
skills/qualifications/expertise, or will these qualities have to be
bought? |
The impression of the Interim Manager of Social Services was
that there were good staff within the Directorate. |
| Budgetary information is provided to this
Committee regularly. Will the savings arising from the Change Plan
be reported separately, although it was acknowledged that the
savings may not materialise for some time. |
There will be regular reporting to both Cabinet and Scrutiny
Committees. |
Following the conclusion of the question and answer, the
Chairman thanked all present for their constructive debate, and
wished officers well in the task before them.
RECOMMENDED- THAT the Report be noted.
850 TAKING FORWARD SUSTAINABILITY (REF) -
Cabinet on 17 January 2007 received an update on progress in
co-ordinating sustainable development in the Council and agreement
was sough for new roles for Cabinet and Scrutiny.
It was reported that revised guidance for the Wales Programme
for Improvement, published in December 2005, introduced new
responsibilities for Councils to assess progress towards
sustainability objectives within the annual Improvement Plan.
Sustainability was also linked to the Making the Connections
agenda, as it was seen as a key component of efficiency and
procurement. Efficiency would, in future, be defined in terms of
whole-life and whole-systems costs. Sustainability was also linked
to engagement, defining resources more broadly and using them
sparingly, building and drawing on community resources, seeking
synergies and favouring renewable and self-sustaining sources.
The role of the Wales Audit Office would be to assess continuing
progress against sustainability objectives. Within the Joint Risk
Assessment, sustainability would be more rigorously assessed.
The Deputy Leader had been identified as the Cabinet Member with
responsibility for progressing sustainable development.
In the Corporate Plan, the Council’s working definition of
sustainability had been agreed as:
· Ensuring a strong, healthy and just society – meeting the
diverse needs of all people in existing and future communities,
promoting personal wellbeing, social cohesion and inclusion, and
creating equality of opportunity for all;
· Achieving a sustainable economy – building a strong, stable
and sustainable economy which provided prosperity and opportunities
for all, and in which environmental and social costs fell on those
who imposed them (polluter pays), and efficient resource use was
incentivised;
· Living within environment limits – respecting the limits of
the planet’s environment, resources and biodiversity – to improve
our environment and ensure that the natural resources needed for
life were unimpaired and remained so for future generations;
· Promoting good governance – actively promoting effective,
participative systems of governance in all levels of society –
engaging people’s creativity, energy and diversity.
An officer working group had been established to:
· provide a strategic focus for sustainable development within
the Council;
· co-ordinate the work necessary to embed sustainable
development across the Council;
· build understanding and awareness of the importance of doing
things in sustainable ways and achieving sustainable outcomes;
· identify and share examples of good practice from within the
Council and from other organisations;
· establish ambitions and aspirations for sustainability within
the Council.
The working group had agreed an action plan, attached at
Appendix 1 to the report. In order to establish effective scrutiny
of sustainable development, the working group was proposing that
one Scrutiny Committee be identified to scrutinise sustainable
development. In the past, this responsibility had been divided
between all Scrutiny Committees, with a resulting loss of focus.
With such a wide definition of sustainability, only the Scrutiny
Committee (Corporate Resources) currently had a wide enough remit
to take on this vital role.
Cabinet had
RESOLVED -
(1) THAT the Action Plan for the Sustainable Development Working
Group be endorsed.
(2) THAT the Scrutiny Committee (Corporate Resources) be
requested to undertake responsibility for scrutinising sustainable
development.
Having considered the decision of Cabinet, Scrutiny
Committee
RECOMMENDED - T H A T the request of Cabinet that Scrutiny
Committee (Corporate Resources) be requested to undertake
responsibility for scrutinising sustainable development be
accepted.
851 CITIZENS PANEL (CX) -
Committee received a report which outlined the purpose and work
of the Citizens’ Panel.
Consulting with the public was key to ensuring that the services
delivered by the Vale of Glamorgan Council met local needs. The
Citizens’ Panel was a way of tapping into public opinion and
understanding the perceptions of the local population. The
Citizens’ Panel had been in place since 2000 and currently had
nearly 1,300 members. Panel members were all residents of the Vale
of Glamorgan (but may not be elected members of staff) and were
consulted regularly on a variety of topics and issues. All Panel
members had agreed to take part in regular consultation activities
and therefore high response rates could be relied upon.
In the past two years, the Panel had been involved in the
following consultation activities:
· Race Equality First community research
· Community safety research
· Visible services – waste management and cleansing, highway
maintenance and parks and grounds maintenance.
· A review of the Citizens’ Panel
· Fire and rescue service focus groups
· Kerbside recycling
· Leisure and tourism research
· Waste peer review
· Public opinion survey
· New library community space usage
· Adult learning opportunities
Approximately six questionnaires or surveys were sent to Panel
members each year, and generally required very little time to
complete and therefore being a Panel member was not a large
commitment in terms of an individual’s time.
Committee were informed of how representative the Panel was when
compared to the Vale population as a whole. These statistics
demonstrated that in terms of ethnicity and disability, the Panel
was not too far from being entirely representative. In terms of the
age profile of the Panel, the Panel currently had an older profile,
with a significant proportion of members being aged over 60.
Panel membership was regularly reviewed, and residents were only
members of the Panel for two years.
· Efforts were being made to try and make the Panel more
representative, particularly by targeted recruitment of younger
people through leaflet campaigns and contacting appropriate local
organisations.
· A Panel for young people aged between 11-16 was being
established.
· Membership would also be reviewed to ensure that people who
had been members for more than two years were removed from the
Panel and new members were recruited.
RECOMMENDED- T H A T the work of the Citizens’ Panel and the
efforts being made to make it more representative be noted.
852 QUARTERLY PERFORMANCE MANAGEMENT MONITORING – CHIEF
EXECUTIVE’S DEPARTMENT- THIRD QUARTER (CX) -
Consideration was given to information relating to the action
plan monitoring and performance indicators contained in the
quarterly performance monitoring reports in respect of the Chief
Executive’s Department for the above period.
Members enquired if they could receive a presentation on
progress being made with the Council’s website.
RECOMMENDED
(1) T H A T the quarterly performance monitoring report for the
period 1 April – 30 December 2006 in respect of the Chief
Executive’s Department be noted.
(2) T H A T members of the Committee receive a presentation in
relation to the Council’s website.
853 BARRY TOWN HALL POST IMPLEMENTATION REVIEW (DEER)
-
Committee were provided with a post implementation review of the
Town Hall Scheme in accordance with Committee’s earlier
request.
Scrutiny Committee (Corporate Resources) in 2006 had carried out
a review of major Corporate projects undertaken by the Council. The
review had considered three areas in relation to Corporate
projects, namely the general management of the project, partnership
working and the levels of external funding and access to
grants.
The findings of the research, amongst other things, had
concluded that whilst members saw regular reports on how projects
were progressing financially there was no reporting or evaluation
on the impact that the Corporate projects had on the wider
community it served, either at inception or completion of the
project.
As part of the management of the implementation of the physical
project, the project management unit required the consultant
project team to carry out a post project analysis of the scheme and
to reach a consensus on what lessons might be learned from the
manner in which the project proceeded. A workshop was held in
October 2006 which was one month after practical completion, but
prior to full occupation and use of the buildings and car park and
the Square that opened in November 2006.
The workshop had set out frame work for evaluating the scheme
against a set of key delivery success factors in order that it
identify and assess obstacles and risks which occurred and to
develop learning points to apply to future projects. The success
factor profile considered the following criteria:
· Purpose
· Appraisal
· Precedent
· Definition
· Management
· People
· Communication
· Procurement
· Design
· Cost Management
· Programme
· Risk.
The overall assessment of the project was positive and on the
majority of the criteria concerned the project scored highly. The
project team assessed eight out of twelve of the success factors as
green and four as amber. There were no red scores across the entire
review. The input to the workshop acknowledged that the
design-procedure-construction processes were very challenging and
that this had led to some stressful episodes. However, what came
across clearly was the immense pride and satisfaction within the
team at the resulting building and parklands. It was felt that the
quality of the completed project had remained true to the original
aspirations despite resulting cost and programme overruns.
RECOMMENDED -
(1) T H A T the contents of the report be noted.
(2) T H A T the relevant operational managers produce a further
report to the Scrutiny (Corporate) Resources Committee at a later
date providing a post project review in respect of operational
matters.
854 UPDATE ON MAJOR PROJECTS (DEER) -
Scrutiny Committee (Corporate Resources) had previously asked
that the Project Management Unit provide a quarterly briefing note
to Cabinet and Scrutiny Committee (Corporate Resources) on current
major corporate projects and upon completion of a project (or a
phase) and assessment on the impact on the relevant community.
Attached to the report was a draft Cabinet Report with
attachments referring to the following lists of projects:
· Barry Town Hall
· Penarth Heights
· Thompson Street Bridge
· Waterfront Innovation Quarter
· Business Support Centre Barry Waterfront
· Hydraulic Pump House, Barry Waterfront
· Medical Centre, Barry Waterfront
· Barry Steam Railway Project
· Central Station Project Phase One Barry Docks platform
· Catching the wave initiative, Barry Marina options
· UWIC
· Wales International Centre for Tourism and Leisure
· The Knap landscaping scheme
· Penarth Pier Pavilion and Italian Shelter
· Former bus depot, Broad Street
· Barry Island Footbridge and Plymouth Road access
Having considered the draft report to Cabinet, members expressed
the view :
1. That the production of such reports on a quarterly basis may
be too onerous and production of on an annual basis may be more
appropriate.
2. That a more appropriate definition of a major project would
be:
“A large or complex project that managed the following
criteria:
· An element of possible large financial risk.
· The comprehensive assessment and management of other risk
factors.
· The need for a corporate overview and set up of corporate
management structures to take the scheme forward.
· The need for the creation or utilisation of external networks
to facilitate the scheme.
· The creation of a wide ranging team, either internal or
external, to manage a large number of complex issues.
· Dedicated resources that are not readily available within
existing service delivery frameworks or staff structures.”
RECOMMENDED – T H A T subject to the above views the content of
the report be noted.
855 QUARTERLY PERFORMANCE MONITORING – THIRD QUARTER –
HUMAN RESOURCES AND EQUALITIES (DLD) -
Consideration was given to information relating to the action
plan monitoring and performance indicators contained in the
quarterly performance monitoring reports in respect of Human
Resources and Equalities for the above period.
Consideration was given to those actions slipped and the
corrective action required and to those indicators not currently
achieving target.
RECOMMENDED – T H A T quarterly performance monitoring report
for the period 1 April – 30 December 2006 in respect of Human
Resources and Equalities be noted.
856 REVENUE MONITORING FOR THE PERIOD 1 APRIL 2006 – 31
DECEMBER 2006 (DFICTP) –
The projected out turn for the 2006/07 revenue budget was shown
in comparison with the amended revenue budget. The current forecast
was for a deficit of £4,301,000 on the General Fund and an
underspend of £50,000 on the Housing Revenue account.
Learning and Development – there was an anticipated saving of
£120,000 on Education and Schools as had been previously reported.
This had been used to offset the overspending on Lifelong Learning
of £120,000 as previously reported.
Directorate of Community Services – the current forecast for
this Directorate was for an underspend of £50,000.00 on the Housing
Revenue Account and a deficit of £4,634,000 on General Fund
Services.
This deficit of £4,634,000 was made up of the following
projected outturns:
Social Services – there was a projected overspend of £4,704,000
on this service as had been previously reported.
Catering – there was a projected overspend of £130,000 on
catering as had been previously reported.
Private Sector Housing – the under-spending on Private Sector
Housing/Community Safety (£200,000) was mainly attributable to an
increase in subsidy income and savings on staff salaries.
Directorate of Environmental and Economic Regeneration –
included in the figures was an anticipated deficit on Leisure
Management (£150,000) due to significant increases in utilities
costs, on parks maintenance due to the increase in prices charged
by external contractors for grass cutting and verge maintenance
(£120,000) and the additional costs of Ground Staff re: the
Centenary Celebrations at Duffryn Gardens (£50,000) and on Building
Maintenance (Trading Unit) (£180,000) attributed to pricing
policies. These deficits were to be offset from underspends within
the Directorate.
Policy – the underspending of £333,000 was mainly attributable
to additional external interest earned.
RECOMMENDED –T H A T the position with regards to the
Authority’s 2006/07 Revenue Budget be noted.
857 CAPITAL MONITORING FOR THE PERIOD 1ST APRIL 2006 TO
31ST DECEMBER 2006 (DFICTP)
Scrutiny Committee were advised of the progress on the 2006/07
Capital Programme for the period 1st April 2006 to 31st December
2006.
Schemes which were not anticipated to outturn on target
were:
Director of Environmental and Economic Regeneration
Penarth Headland Link
Cowbridge Bypass, Rain Activated Sign
Policy
Disabled Access Audit and Improvements
Housing Advances
Duffryn Gardens
Holton Road Christmas Lighting
In addition, attached at appendix 2 to the report was Non
Financial Information on Capital Schemes with a budget over
£100,000.
RECOMMENDED – T H A T the position with regard to the 2006/07
Capital Programme be noted.
858 QUARTERLY PERFORMANCE MONITORING – THIRD QUARTER –
FINANCE AND PROPERTY (DFICTP)
Consideration was given to the information relating to the
Action Plan Monitoring and Performance Indicators contained in the
Quarterly Performance Monitoring Report in respect of Finance and
Property for the above period.
RECOMMENDED – T H A T the Quarterly Performance Monitoring
Report for the period 1st April – 30th December 2006 in respect of
Finance and Property be noted.
859 QUARTERLY PERFORMANCE MONITORING – THIRD QUARTER – ICT
SERVICES (DFICTP) -
Consideration was given to the information relating to the
Action Plan Monitoring and Performance Indicators contained in the
Quarterly Performance Monitoring Report in respect of ICT Services
for the above period.
RECOMMENDED –T H A T the Quarterly Performance Monitoring Report
for the period 1st April – 30th December 2006 in respect of ICT
Services be noted.