Welcome to the
Vale of Glamorgan Council

SCRUTINY COMMITTEE (LIFELONG LEARNING)

 

Minutes of a meeting held on 10th November, 2008.

 

Present:  Councillor J. Clifford (Chairman); Councillor Mrs. K.A. Kemp (Vice-Chairman); Councillors Mrs. M.E.J. Birch, Mrs. V.L. Ellis, C.P.J. Elmore, E. Hacker, Mrs. V.M. Hartrey, C.L. Osborne and Mrs. S.I. Sharpe.

 

 

522     APOLOGIES FOR ABSENCE -

 

These were received from Councillors A.D. Hampton and F.T. Johnson.

 

 

523     MINUTES -

 

RECOMMENDED - T H A T the minutes of the meeting held on 20th October, 2008 be approved as an accurate record.

 

 

524     DECLARATIONS OF INTEREST -

 

The following Councillors declared the nature of their personal interests, being Governors of schools within the Vale of Glamorgan:

 

Councillors J. Clifford, Mrs. K.A. Kemp, Mrs. M.E.J. Birch, C.P.J. Elmore, E. Hacker, Mrs. V.M. Hartrey and C.L. Osborne.

 

Councillors J. Clifford, C.P.J. Elmore and Mrs. S.I. Sharpe declared an interest in Agenda Item No. 8, Redevelopment of Cowbridge Comprehensive School in that they were Members of the Trust Committee and left the room whilst this item was under consideration.

 

 

525     REDEVELOPMENT OF COWBRIDGE COMPREHENSIVE SCHOOL (DLD) -

 

Mr. Maclean and Mr. Mitchell of Davis Langdon were present for this item.

 

The Chairman vacated the room whilst this item was considered, and the Vice-Chairman took the Chair.

 

Committee received an update on the School Investment Strategy with specific reference to the redevelopment of Cowbridge Comprehensive School.

 

Davis Langdon were appointed as the Council's external design team in September 2007.  They had completed the initial design stages of the school such that a full planning application had been submitted in the summer of 2008.

 

In July 2008, Carillion had been appointed as the contractor to complete the design of Cowbridge Comprehensive School and then subsequently construct the new school using the NEC Engineering and Construction Contract.

 

The aim of Davis Langdon had been to maximise the benefits of the new school development with clear defined financial parameters.  Whilst a creative solution had been developed, nevertheless the availability of options as to how this could be achieved had been restricted by the need to secure value for money.  This had been achieved by a mixture of new build on the Aberthin Road site and retention and refurbishment of existing buildings. 

 

Davis Langdon had been working on the final design to an indicative maximum budget of £21.5 million including all relevant fees.  As a matter of prudence and to ensure deliverability within the design process, Davis Langdon had incorporated a phased approach with the first phase costing £16.5 million, and the option of delivering the second phase at a future date.  However, under a phased option, there was a risk that the second phase would exceed £5 million due to factors such as inflation and the efficiencies in breaking up the construction process and therefore would not be cost-effective.  Davis Langdon had recommended that the school be developed in a single phase. 

 

A report was due to be presented to Cabinet in December that would detail robust costings for the redevelopment of the school.  Approval would be sought to commence construction on the new school.

 

Planning approval would be determined in mid November.  Initial enabling works which were not dependent on planning and which would be required whether the Council approved the £21.5 million scheme in full or the phased delivery function, were likely to be commenced before the end of October, 2008.  This would benefit the delivery of the school within agreed timescales to enable co-location for the September 2010 deadline.

 

The representatives of Davis Langdon offered an opportunity to Members to ask questions, whereupon it was

 

RECOMMENDED - T H A T the presentation and report be noted.

 

Reason for recommendation

 

That Members are aware of progress on the Redevelopment of Cowbridge Comprehensive School.

 

 

526     DRAFT SUPPLEMENTARY PLANNING GUIDANCE ON PLANNING OBLIGATIONS (REF) -

 

Councillor J. Clifford returned to the room and took the Chair for the remainder of the meeting.

 

The above matter had been considered previously at the meeting of the Cabinet held on 17th September, 2008 and latterly at the Scrutiny Committee (Economy and Environment) on 14th October, 2008.  This Scrutiny Committee had subsequently recommended that the report be referred to all the Council's Scrutiny Committees to obtain their observations on those matters falling within each of the Scrutiny Committees remits and to report their comments back to the Scrutiny Committee (Economy and Environment) as soon as practicably possible. 

 

Having regard to the above, it was noted that the Draft Supplementary Planning Guidance (SPG) on Planning Obligations was appended to the report of which the document also contained an introduction to Planning Obligations and their use within the Vale of Glamorgan.  The draft SPG also outlined those matters that were likely to be sought for and related processes when dealing with planning applications.  The SPG had a series of topic specific appendices detailing the Council's approach to the following issues:

 

·         affordable housing

·         community facilities

·         education/training and development

·         public open space, public arts and recreation

·         town centres and regeneration

·         transport and waste and recycling facilities.

 

The purpose of the introduction of the Planning Obligations SPG was to clarify for all interested persons the Council's approach to seeking and monitoring Planning Obligations.  This approach was consistent to those taken by other Planning Authorities in England and Wales and within the context of recent advice sponsored by the Planning Officers Society for Wales.

 

The SPG contained formulas for specific topics covered within the guidance.  Those formulas had been calculated through an assessment of what it would cost to provide facilities in association with developments and experience as to what would be reasonable to seek through negotiations depending on the scale and form of the development and the current state of the market.

 

Having regard to the above and related issues it was

 

RECOMMENDED - T H A T the draft Supplementary Planning Guidance on Planning Obligations be endorsed.

 

Reason for decision

 

To inform the Members of the Scrutiny Committee (Economy and Environment) of the views of the Scrutiny Committee (Lifelong Learning) prior to the adoption of the draft SPG.

 

 

527     VOLUNTARY ACTION SCHEME PRIORITIES FOR FUNDING 2009/10 (DFICTP) -

 

Committee were informed of the amended priorities for funding under the Voluntary Action Scheme for the year 2009/10. 

 

The arrangements and priorities for funding in 2009/10 had been considered by the Voluntary Sector Joint Liaison Committee on 22nd July, 2008 and had been approved by Cabinet on 1st October, 2008.

 

A part of the mechanism for consideration of applications it was Committee's practice to seek the views of the various Council partnerships appropriate to the applications. 

 

Some of the partnerships had revised their priorities in line with the new Strategies for April 2008, for example, the Children and Young People's Plan 2008/11 the Health, Social Care and Wellbeing Strategy 2008/11.  The new key themes in these plans provided the priorities for the Council's work in 2009/10.

 

It was appropriate therefore, that the Council funded the voluntary sector projects which met these priorities and which furthered the work which would benefit Vale residents under the key themes.

 

The Partnership Co-ordinators had proposed that prospective applicants for funding make contact with the most appropriate Co-ordinators prior to completing their applications.  This would help the applicants to apply for funding for projects in line with the Council's key priorities for funding.  It would ensure that the Council funded projects from the scheme which were in keeping with its 2009/10 key themes for developing services.

 

RECOMMENDED - T H A T the priorities for funding 2009/10 be noted.

 

Reason for recommendation

 

To progress the Voluntary Action Scheme 2009/10.

 

 

528     SCRUTINY COMMITTEE - TRACKING OF RECOMMENDATIONS (DLPPHS) -

 

Members were informed of the progress in relation to uncompleted recommendations that had been made by the Committee during the period April 2007 to March 2008 (attached at Appendix A to the report) and the for quarters April to June 2008 and July to September 2008 (attached at Appendix B to the report).

 

The following issues were then discussed with a number of the recommendations being agreed as being completed, as detailed below:

 

28 July 2008 - Min. No. 199

Inspection of the Youth Offending Service (CX) -

Recommended -

 

(2)       That the Chairman or Vice-Chairman of Scrutiny Committee (Lifelong Learning) be invited to attend the meetings of the Workshops as identified in the Action Plan.

Action Completed

(3)       That further consideration be given to the possibility of the inclusion of an item relating to the YOS within the Committee's forthcoming Work Programme.

Action Completed

28 July 2008 - Min. No. 201

Scrutiny Committee Work Programme (DLD) - Recommended - That the Chairman and Vice-Chairman of the Scrutiny Committee (Lifelong Learning) be granted authority to:

 

(2)       Identify a specific issue for independent review by the Improvement and Development Team.

Action Completed

(3)       Produce a timetable for the work programme.

Action Completed

28 July 2008 - Min. No. 204

Scrutiny Committee Performance Panels (CX) - Recommended -

 

(1)       That a specialist Performance Panel to examine and evaluate performance information on a quarterly basis be established for the Scrutiny Committee (Lifelong Learning)

Action Completed

10 September 2007 - Min. No. 318

Revenue and Capital Monitoring for the Period 1st April to 31st July 2007 (DLD) - Recommended

 

(3)       That a report be presented to the Scrutiny Committee in respect of issues relating to school transport contracts and any implications as a result of the current contractors termination of contract.

Action Completed

8 October 2007 - Min. No. 414

Revenue and Capital Monitoring for the Period 1st April, 2007 to 31st August, 2007 (DLD) - Recommended

 

 

(2)       That a report on the operation of Breakfast Clubs within the Vale of Glamorgan such report to also include details of the funding, be brought before the January 2008 meeting of this Committee.

Action Completed

21 January 2008 - Min No. 728

Scrutiny Committee Action Plan (DLD) - Recommended

 

(1)       That the Director of Learning and Development provide a report detailing of progress on the strategic issues detailed above and that this be reviewed on a quarterly basis by Scrutiny Committee.

Action Completed

 

(3)       That, in addition to the above, the Director of Learning and Development provide information reports on Foundation Phase, 14 -19 and Exclusions to Scrutiny Committee meetings before May 2008.

Action Completed

These reports would inform the post May Action Plan of the Committee.

 

 

 

529     PRESENTATION ON THE PULSE PROJECT (DLD) -

 

Hannah Wilcox, Co-ordinator of the Pulse Project provided an outline of the work of the service.

 

Following an application to the 'Reaching Out' stream of the National Lottery, funding had been received for a period of three years to run a Vale wide detached youth project working with 10-19 year olds.  Pulse formed part of the Vale of Glamorgan's Youth Service and was steered by Community Safety Partnerships Youth Issues Group. 

 

It was reported that Pulse:

 

·         used detached youth work as a means to reach and work with young people across the Vale on their territory

·         engaged with young people on their terms, in their environment

·         worked with young people to explore their needs and provide opportunities for self development

·         provided informed, accurate and appropriate advice and information for young people on their terms in an informal detached setting

·        aimed to meet the needs of the young people through creative, flexible and good quality youth work

·        used positive engagement, encouragement and support to help safeguard young people's wellbeing.

 

During the period October 2007 - October 2008 Pulse had

 

·        made 4733 contacts with 10-19 year olds

·        provided 1593 young people with local information about their area

·        signposted 324 young people to specialist services

·        involved 2300 young people in diversionary activities.

 

In addition, Pulse had targeted efforts towards areas of specific need such as Halloween, and also had an active involvement with in excess of 30 Vale-wide partnership organisations including Women's Aid, Vibe Experience, Salvation Army, MoD St. Athan and RAF St. Athan.

 

As far as the future was concerned, Big Lottery Funding would continue until November 2009.  Following the conclusion of the funding, it was reported that there was a possibility that limited Safer Vale funding could be commissioned. 

 

Discussions ensued on the work of Pulse i.e.

 

How many staff are involved in Pulse?

Six full time

Five part time

 

Can areas of need be reported to Pulse?

Yes.  Pulse will prepare a course of action to assist areas of need.

 

Do you have plans for Sully?

All Wards of the Council will receive visits from Pulse by the time funding ceases.

 

Congratulations to Pulse for achieving the recent Team of the Year Award.

 

 

The Chairman and Members of the Committee thanked Hannah for her presentation.

Vale of Glamorgan Council, Civic Offices, Holton Road, Barry CF63 4RU, Tel: (01446) 700111