The Vale of Glamorgan Council
Cabinet : 3rd December 2008
Director of Learning and Development
Re-Development of Cowbridge Comprehensive School
Purpose of the Report
1.
To seek approval to commence the construction and re-development of
Cowbridge Comprehensive School.
Recommendations
1.
That Cabinet approve commencement of the construction and
re-development of Cowbridge Comprehensive School. In
accordance with the budgeted affordability discussed in Paras 4 to
16, the Council proceed with the £16.5 million phase of the
development immediately and continue to identify the funding
necessary to finalise the development by September 2010 or as soon
as possible thereafter.
2.
That Cabinet approve that the Director of Legal, Public Protection
& Housing in consultation with the Director of Finance, ICT
& Property be authorised to prepare, complete and execute the
appropriate contractual details with Carillion in relation to Phase
1 of the construction and redevelopment of Cowbridge Comprehensive
School.
Reasons for the Recommendations
1.
To complete the re-development project at Cowbridge making the
school fit for purpose whilst at the same time discharging the
Council's statutory responsibilities in respect of school
buildings.
2.
To ensure that appropriate contractual arrangements are in
place.
Background
2.
Davis Langdon were appointed as the Council's Project Managers to
lead the external design team in September 2007. They
completed the initial design stages of the school such that a full
planning application was submitted in the Summer of 2008 and
subsequently approved in November 2008.
3.
In July 2008, using the New Engineering Contract (NEC) Professional
Services Contract, Carillion were appointed as the contractor to
complete the design of Cowbridge Comprehensive School and then
subsequently construct the new school using the NEC Engineering and
Construction Contract. The benefits of the New Engineering
Contract in terms of value for money and cost control were reported
to Cabinet in July 2008. At present, beyond
finalisation of the design stage and associated costing, the
Council is not committed to the construction stage.
Relevant Issues and Options
4.
Davis Langdon and the design team have designed and planned the
re-development of Cowbridge School. The design allows for a
single phase development within a maximum targeted budget of £21.5
million. However, in order for the single phased development
to be delivered, it is a requisite that the Council have secured
the £21.5 million in full.
5.
A full breakdown of the £21.5 million costs are available on
request. The programme provides £205,800 for a temporary
sports hall and a contribution of £300,000 towards fixtures,
furnishings and equipment. The temporary sports hall will be
required until the summer of 2010. Although temporary, the
sports hall is nevertheless a robust structure with a life
expectancy in excess of 25 years. It is envisaged that the
temporary sports hall would be re-located to another school once
the re-development of Cowbridge was complete. The school
would be co-located on a single site via new build, with playing
fields being provided adjacent to the school. The canteen and
administration block, together with the three existing newer
teaching blocks would all be refurbished. There would be a
high degree of landscaping, with new car and bus parking
arrangements, supported by new access roadways.
6.
With regard to Fixtures, Furnishings and Equipment, it is estimated
that the maximum cost would be £600,000. It has always been
envisaged that part of this cost in relation to loose fixtures,
furnishings and equipment (i.e. £300,000) would be funded from
elsewhere within the education budget. For instance, the
£300,000 could be funded from reserves in the first instance and
clawed back from the schools' split site allocation which will
cease when the school operates from a single site. Currently
the split site allocation is equivalent to almost £90,000.
7.
In order to ensure affordability in respect of the availability and
timing of resources, Davis Langdon and the design team also
prepared a phased delivery. Phase 1 of this approach is
costed at a maximum of £16.5 million. A full breakdown of
these costs are available upon request. The Phase
1 costings includes the temporary sports hall (£205,800) which can
subsequently be used at another school together with a contribution
of £125,000 towards Fixtures, Furnishings and Equipment. The
maximum requirement for Phase 1 Fixtures, Furnishings and Equipment
would be £450,000.
8.
The £16.5 million phase of the development would include the same
level of new build as the full £21.5 million scheme with the school
buildings being co-located on a single site, as well as the same
level of car parking, bus parking and access roads. There
would also be the provision of a new canteen within the existing
administration block. However, the £16.5 million phase does
not include completion of the playing fields so that the school
would need to continue to use the playing fields adjacent to the
Townmill Road site. This would mean that the school would
retain a portion of their split site allocation. Also there
would be limited refurbishment of the existing blocks. There would
also be a reduction in landscaping.
9.
Excluding inflationary consequences, it is estimated that once the
£16.5 million phase is completed, finalising the development could
cost a further £6.48 million bringing the total cost to deliver the
facilities required to £22.98 million. Final costs would
depend upon the time-scale for completing the development.
10. In terms of
prioritising work not included within the £16.5 million scheme,
Davis Langdon and the design team have recommended the
following:-
· Refurbishment of
existing buildings
· Playing fields
· Landscaping
11. The cost of the above
works will be dependent on when the works are carried out and will
need to be contracted when funds are available.
12. Both the £21.5
million and £16.5 million developments provide a high level of cost
certainty. With respect to the £21.5 project, 89.28% of the
construction cost is fixed and will not change. The 10.72%
costs that are still variable will be capped at the current budget
levels. For the £16.5 million development, 92.58% of the
construction cost is fixed and will not change. The 7.42% of
costs that are still variable will be capped at current budget
levels. The £21.5 million scheme provides for a client
contingency of nearly £500,000 which is a prudent level for a
construction contract of this type, whilst the £16.5 million scheme
only provides for a contingency of around £120,000. In term
of the management of risk, risk registers for both options have
been prepared.
Resource Implications (Financial and Employment)
13. To date the Council
has identified a total of £16.5 million secured funding. This
is summarised in the table below.
|
|
£'million
|
|
Welsh Assembly Government School Building
Improvement Grant
|
9.0
|
|
Council's Capital Receipts Realised
|
1.4
|
|
Council's Education Reserves
|
3.6
|
|
Council's Supported Borrowing
|
2.5
|
|
Total
|
16.5
|
14. As Members are aware,
the Cowbridge Trust is in the process of obtaining appropriate
advice to enable detailed discussions with the Charity Commission
to take place with a view to requesting that the Commission consent
to any sale proceeds generated from the possible sale of the Trust
land at the Lower School Site be reinvested into the redevelopment
and construction of the Upper School Site.
15. The Council has had
very limited success with respect to the generation of capital
receipts. The only current possibility relates to the
disposal of the sixth form building and adjacent land which will be
vacant once the school is re-developed. However, it is
unlikely that this would realise more than £0.5 million and
possibly significantly less in the current climate.
16. The use of prudential
borrowing to generate the shortfall of £5 million funding, would
commit the Council to an annual revenue repayment of £0.5 million
for a period of up to 25 years. In light of the severe
financial pressures facing the education and school budgets, and
indeed the Council as a whole, prudential borrowing would represent
a high risk strategy.
17. The single phased
option of £21.5 million provides for a contribution of £300,000
towards furniture and fittings and a contingency of nearly £0.5
million. The first phased option of £16.5 million provides a
contribution of £125,000 towards furniture and fittings and a
contingency of just under £0.12 million. It is estimated that
Fixtures, Furniture and Equipment could be as high as £600,000 for
the £21.5 million option and £450,000 for the £16.5 million
option. The differences of £300,000 and £325,000 respectively
would need to be met from education reserves and cessation of
split-site funding.
18. Efforts are currently
in hand to identify the additional funding to deliver the full
development of the school for September 2010 or as soon as possible
thereafter. However, in order to secure the £9.0 million
School Buildings Improvement Grant, and not lose it, the Council
must decide to proceed with at least the £16.5 million scheme.
Legal Implications (to Include Human Rights Implications)
19. Approval to proceed
to the construction stage of the project would require a standard
form legal contract between the Council and Carillion Building (NEC
Contract).
Crime and Disorder Implications
20. Improved School
Buildings would have a positive effect on Crime and Disorder.
Equal Opportunities Implications (to include Welsh Language
issues)
21. Improved School
Buildings will enhance equality of opportunity.
Corporate/Service Objectives
22. The re-development of
Cowbridge School is a corporate priority.
Policy Framework and Budget
23. This is a matter for
executive decision.
Consultation (including Ward Member Consultation)
24. Relevant Ward Members
have been consulted. One Member is in full support of the
project and hopes that the full amount needed to deliver the whole
scheme can be identified. Another Member is fully supportive
of a single phased approach.
Relevant Scrutiny Committee
25. Lifelong
Learning.
Background Papers
Contact Officer
Martin Donovan
Head of Strategic Planning and Performance
01446 709161
Officers Consulted
Responsible Officer:
Bryan Jeffreys
Director of Learning and Development