SCRUTINY COMMITTEE (ECONOMY AND
ENVIRONMENT)
Minutes of a meeting held on 6th
December, 2011.
Present: Councillor C.J. Williams
(Chairman); Councillor Mrs. M. Kelly Owen (Vice-Chairman);
Councillors Ms. M.E. Alexander, J.C. Bird, R.F. Curtis,
G. John, Mrs. S.I. Sharpe, M.R. Wilson and Ms. M.
Wright.
Also present: Councillor N. Moore.
669 APOLOGIES FOR
ABSENCE -
These were received from Councillors Mrs. A.J.
Preston and R.P. Thomas.
670 MINUTES -
RECOMMENDED - T H A T the minutes of the
meeting held on 1st November, 2011 be approved as a
correct record.
671 DECLARATIONS OF
INTEREST -
No declarations were received.
672 INITIAL CAPITAL
PROGRAMME PROPOSALS 2012/13 AND INITIAL REVENUE BUDGET PROPOSALS
2012/13 (REFERENCES - CABINET 16TH NOVEMBER, 2011)
-
RECOMMENDED - T H A T the references be noted
and considered jointly with the reports at agenda items 6 and
7.
673 INITIAL CAPITAL
PROGRAMME PROPOSALS 2012/13 (DEER) -
The Cabinet reference and the report were
considered by the Committee with it being noted that the
initial proposals were presented to the Committee for consideration
and that any recommendations were to be referred to the Corporate
Resources Scrutiny Committee by no later than 20th
December 2011. The final budget proposals were scheduled to
be presented to Cabinet by no later than 29th February,
2012 with submission to Council by no later than 7th
March 2012.
The Head of Accountancy and Resource
Management presented the report advising that Appendix A to the
report detailed the financial progress on the Capital Programme as
at 30th September 2011. The report also noted that
with regard to the Barry Waterfront Park and Ride Additional
Design, an additional grant sum of £46,000 for the scheme had been
agreed by SEWTA to cover additional costs on the main contract sum
and design and management fees due to additional works required on
drainage, redesigning following the planning procedure and ecology
related fees. The Authority had also received grant funding
of £74,792 to provide support for capital initiatives to achieve
increased waste prevention and improve recycling initiatives under
the Regional Capital Access fund. It was intended that the
capital funding would be used for a new recycling vehicle and the
procurement process was being progressed by the Council’s Fleet
Management Section. Although tenders had not yet been
received, it was anticipated that the vehicle would cost slightly
more than the available grant and, as such, a contribution from
revenue budgets of up to £30,000 would be needed. Cabinet had
also previously agreed that further information would be provided
where schemes had a value of over £500,000 and showed a variance of
20% or more between actual spend and the profile. It was
noted that the following schemes had met this criteria:
- Llanmaes Flood Risk Management - Members were
advised that despite having received funding for the Coldbrook
Catchment Flood Management Scheme, it was extremely unlikely that
grant funding for the Llanmaes scheme would be forthcoming this
year. The Director of Environmental and Economic Regeneration
would be addressing this issue shortly in a Cabinet report on both
the Coldbrook and Llanmaes Flooding Schemes shortly. Councillor G
John requested that the Head of Service kept Llanmaes Community
Council informed on the matter.
- Vehicle Renewal Programme - expenditure on
the budget was behind profile and the Head of Service advised that
the original “All Wales Public Sector Framework Agreement for the
Acquisition of Commercial Vehicles” had been replaced by the
Yorkshire Purchasing Organisation although the arrangement had not
formally been accepted by the All Wales Fleet and Transport
Managers Group and Welsh Purchasing Consortium which had caused a
delay in the purchasing of vehicles in the financial year
2011/12. Whilst every effort was being made to maximise
expenditure on this budget, the Fleet Manager had advised that
there could potentially be some underspend at the year
end.
Appendix B to the report outlined the proposed
2012/13 Capital Programme. Members were advised that the bids
would have to be evaluated for sustainable development under the
headings:
- living within environmental limits
- ensuring a strong, healthy and just
society
- achieving a sustainable economy
- promoting good governance.
Sustainability checklists would also be
requested from Project Managers for each of the bids
detailed. They would be reviewed by members of the
Sustainable Development Working Group with a view to ensuring that
wherever possible the four sustainable targets were
addressed. The results would be included in the final Capital
proposals report in February 2012.
The Budget Working Group had prioritised the
bids based upon the recommendations of the Corporate Asset
Management Group with the method of prioritisation as follows:
|
A
|
|
Health and Safety Legislation
|
|
B
|
|
Other Legislation / Statutory requirement
|
|
Ci
|
|
Economic Sense
|
|
Cii
|
|
Corporate Plan
|
|
Ciii
|
|
Sufficiency
|
|
D
|
|
Condition / Suitability
|
|
E
|
|
Welsh Government objectives
|
|
F
|
|
Low Priority
|
In considering the report reference was made
to the Dingle Road Bridge with Members being informed that it was
the intention to fund a replacement via the Section 106 agreement
from Penarth Heights. Members also sought clarification on
the criteria used to assess the need to refurbish children's play
areas and were advised that the £100,000 detailed in the report
referred to a generic fund for asset renewal which would be spent
on a needs basis. An inventory of all play areas had also been
undertaken and priorities had been identified. The Old Harbour
revetment referred to at Appendix C related to general maintenance
on the Harbour wall. With regard to the partnership agreement
with leisure centres, the Director of Environmental and Economic
Regeneration advised Members that the process had been delayed due
to the slippage in the job evaluation process but discussions
were ongoing regarding staff salaries and terms and conditions,
etc. Tenders had also been received approximately six weeks
previously and a consultancy firm were currently assessing the
tenders with a view to a report being presented to Cabinet and the
Scrutiny Committee following the evaluation process.
The Principal Regeneration Officer advised the
Committee of some good news that had been received that day in
relation to the Barry Island Footbridge in that £500,000 had been
confirmed by the Department for Transport although clarification of
the preferred contractor status needed to be ascertained in view of
the fact the original tender had been submitted in 2009.
The Chairman referred to a fatality that had
recently taken place on the road from Barry to Dinas Powys and
suggested that the Cabinet be requested to consider the provision
of a cycle path on this stretch of road on the grounds of health
and safety. He suggested that the Cabinet could consider
funding this provision from the Vehicle Renewal programme in view
of the delay on the spend in that budget. The Chairman further
suggested that the speed limit on the road should be reduced to
40mph in light of the recent fatality and other accidents that had
taken place in the area.
In referring to Appendix B and the budget for
substandard bridges the Chairman expressed his disappointment that
Cross Common Road bridge had not been noted separately in the bids
and that only £250,000 would be made available for bridge
maintenance when he was aware that the cost for Cross Common bridge
had previously been reported to be in the region of over £600,000
on its own.
Councillor Wilson referred to the bus lane at
the Merrie Harrier junction Dinas Powys in that the traffic flow,
bus lane and filtering arrangements were problematic and required
further consideration.
Following consideration of the report it was
subsequently
RECOMMENDED - T H A T the Scrutiny Committee
(Corporate Resources) and Cabinet be requested to consider
(1) T H AT
a pedestrian and cycle path route be provided on the stretch of
road from Barry to Dinas Powys ie on the A4055 from Biglis
roundabout to Southra Park Estate.
(2) T H A
T a full options appraisal be undertaken on the A4055 from the
Biglis roundabout through Dinas Powys to the Merrie Harrier
junction.
Reasons for recommendations
(1) To
establish a walking and cycling path urgently on health and safety
grounds.
(2) In
order that a full assessment of the areas can be undertaken.
674 INITIAL REVENUE
BUDGET PROPOSALS 2012/13 (DEER) -
The reference from Cabinet of 16th
November, 2011 and the report were considered jointly in view of
the need to refer any comments to the Scrutiny Committee (Corporate
Resources) and the Cabinet.
Appendix 1 to the report set out the necessary
transfers to the original estimate for 2011/12 which were required
to be made as follows:
- Asset Rents, International Accounting
Standard (IAS) 19, and Recharges etc - these related to accounting
items and expenditure outside the control of Services. They
reflected charges to Services for the use of capital assets,
changes to inter service recharges, superannuation increases not
required and adjustments in respect of pensions to comply with
accounting standards.
- Transfers – these reflected in the main
transfers of functions and responsibilities between services ie the
transfer of £1.869m from the Education and Schools (Strategy and
Performance) budget to the E&ER Directorate (Planning and
Transportation) budget to ensure budgets more accurately reflected
accountability and delivery responsibilities for Mainstream
Transport.
The following table compared the amended
original budget with the projected outturn for 2011/12:
|
|
2011/12
|
2011/12
|
Variance
|
|
|
Amended
Original
|
Projected
|
(+)Favourable
|
|
Directorate/Service
|
Budget
|
Outturn
|
(-)
Adverse
|
|
|
£’000
|
£’000
|
£’000
|
|
|
|
|
|
|
Environmental and Economic Regeneration
|
|
|
|
|
Planning and
Transportation
|
4,928
|
4,982
|
(-)54
|
|
Economic Development and Leisure
|
7,028
|
7,394
|
(-)366
|
|
Visible Services
|
21,224
|
21,054
|
(+)170
|
|
|
|
|
|
|
Grand Total
|
33,180
|
33,430
|
(-)250
|
It was noted that for Planning and
Transportation there was an adverse variance of £54k. due to
increased supplies and services and premises costs of £76k. mainly
due to the inclusion of Local Road Safety Grant expenditure within
the estimates. Transport costs had also increased by £50k.
primarily as a result of the increasing costs of providing home to
school transport. The projected outturn for Economic
Development and Leisure Department showed an adverse variance of
£366k. which was mainly attributable to supplies and services and
employees, including one off costs of £92k. that had been incurred
as a result of the proposed Leisure Centre Partnership and transfer
of Dyffryn Gardens to the National Trust. Visible Services
showed a favourable variance of £170k. with the Head of Service
also holding a budget for any pressures that may arise during the
financial year. However, premises and repairs budgets were
projected to overspend by £663k. being mainly attributable to the
level of repairs required to the highway network as a consequence
of the last two severe winters plus there had been an increase of
18% in Street Lighting energy costs for 2011/12. A total of
£380k. of reserves was to be used to help fund the increased cost
of repairing the highway and the increased cost of street lighting
energy.
In considering the report Members commented on
the need to be more efficient and effective in relation to street
lighting and the use of LED lights. With regard to school
transport, the Director advised that the bulk of the spend related
to the Councils statutory duty with the cost of providing a bus
service increasing, particularly in view of increasing fuel
costs.
Cost pressures were also highlighted in
relation to the Barry and Cowbridge Markets and officers were due
to meet with representatives to discuss the issue
further.
Members also raised concerns in relation to
the Councils responsibility in relation to the Coast and cliff
erosion. The Director advised that a coastal management plan had
been developed which identified various issues and the Department
was currently discussing in detail with landowners the steps that
could be taken to deal with the issue. .
Although expressing their concern regarding
the cost pressures, Members
RECOMMENDED - T H A T the amended budget as
set out at Appendix 1 to the report be noted.
Reason for recommendation
To note the changes made to projected
spending.
675 DRAFT
SUPPLEMENTARY PLANNING GUIDANCE ON UPPER HOLTON ROAD, BARRY (REF)
-
Cabinet had, on 16th November 2011,
referred the report to the Scrutiny Committee to engage in the
consultation process. Cabinet approval had been sought for
the introduction of the draft Supplementary Planning Guidance on
Upper Holton Road Development Guidelines so that it may be
published for consultation purposes. The Supplementary
Planning Guidance (SPG) was attached as an appendix to the report
with the Principal Regeneration Officer advising that the SPG
sought to establish specific design guidance for the future
development of the Upper Holton Road local centre, as well as
influencing the pattern of land uses within the area. The
draft SPG was one of three initiatives that sought to address
issues that had been identified within the Upper Holton Road,
Barry. The other initiatives were noted as Houses in Multiple
Occupation Licensing Scheme and changes to the Vale of Glamorgan
Council Housing Renewal Area Policy 2010-2013. It was
anticipated that these three initiatives, if adopted, could provide
a clear direction that would assist with the future process of
management, change and improvement for the area.
The general composition of the SPG document
was as follows:
- Background
- Purpose of the Guidance
- Existing national and Local Policy
Guidance
- Identification of Core Retail Area
- Shop Front Design Guidance
- Advertisement Design Guidance
- Design Guidance for the Conversion of
Commercial Premises to Residential
- Information on the need for necessary
consents
- Appendices (containing map of area to which
guidance relates and background information).
The officer also tabled a coloured copy of the
map detailed within the appendices which clarified for Members’ the
specific areas concerned. In presenting the report the
officer also stressed that it should be recognised that various
interested parties, businesses, traders and organisations, would
have the opportunity to respond to the content of the document and
it was anticipated that once the consultation exercise had been
undertaken the report would be presented to Cabinet to set out the
views obtained and the way forward in response to the views
expressed.
The Principal Regeneration Officer also
informed Committee that it was the intention to commence the
consultation exercise week commencing 19th December
and conclude at the end of February 2012. All landlords and
businesses in the red boundary area detailed in the map would be
written to and invited to attend drop in sessions or if requested,
attend face to face meetings with officers, a newsletter would also
be distributed to the Castleland Renewal Area and the proposals
would be conveyed via social media and the website etc.
Having considered the report it was
RECOMMENDED - T H A T the resolutions of
Cabinet be accepted.
Reason for recommendation
In light of the consultation process that
would be undertaken.
676 PROSIECT GWYRDD
MINUTES: 22ND JULY AND 7TH OCTOBER 2011 -
The following minutes of the Prosiect Gwyrdd
Joint Scrutiny Panel were presented for Members’ information:
22nd July, 2011
Present:
Councillor C. J. Williams - Chairman (Vale
of Glamorgan Council)
Councillors:
Councillors R. McKerlich and S. Wakefield (Cardiff County
Council)
Councillors S. Howarth and Ms V. Smith (Monmouthshire County
Council)
Councillor S. Jones (Newport City Council)
Councillor Mrs. M. Kelly-Owen (Vale of Glamorgan
Council)
Together with:
D. Perkins and J. Jones (Caerphilly County Borough Council),
R. Phillips (Cardiff County Council), H. Ilett (Monmouthshire
County Council), D. Collins (Newport City Council), J. Wyatt (Vale
of Glamorgan Council)
Prosiect Gwyrdd Officers:
M. Williams (Project Director), A. Williamson (Technical
Manager), J. Pritchard (Legal Officer), M. Falconer (Finance
Manager), R. Quick (Senior Responsible Officer), I. Lloyd-Davies
(Communications Officer), M. Williams (Caerphilly County Borough
Council)
1.
APOLOGIES FOR ABSENCE
Apologies for absence were received from Councillors M.G.
Parker and D.V. Poole (Caerphilly County Borough Council) and
B. Bright (Newport City Council).
2.
DECLARATIONS OF INTEREST
There were no declarations of interest received at the
commencement or during the course of the meeting.
3.
MINUTES - 11TH MARCH 2011
It was agreed that the minutes of the meeting held on 11th
March 2011 be approved as a correct record.
Matter Arising
Site visits to Facilities
The Project Director advised that the request of the Panel
that the Joint Committee consider and approve visits by the members
of the Panel to the facilities operated by the final two
shortlisted bidders would be considered in the autumn.
EXEMPT MATTER
It was accepted that in this instance the presentation and
subsequent discussions would contain exempt information and that
there would be other occasions when it would be necessary to
exclude the press and public. However, it was intended that where
possible reports would be considered in the open part of the
meeting to enable the public to be present.
Members considered the public interest test certificate from
the Proper Officer and concluded that on balance the public
interest in maintaining the exemption outweighed the public
interest in disclosing the information and it was
RESOLVED that in accordance with Section 100A(4) of the
Local Government Act 1972 the public be excluded from the remainder
of the meeting because of the likely disclosure to them of exempt
information as
identified
in paragraph 19 of Part 4 of Schedule 12A of the Local Government
Act 1972.
PROSIECT GWRYDD PRESENTATION
Mr. M. Williams (Project Director) gave a presentation which
highlighted the commercial sensitivity of the project, the role of
scrutiny, the overall timeline, the current bids, risks and issues
associated with the project, the overall timeline, the joint
working agreement, communications and engagement and the themes of
the work programme.
To put the project into context he advised that the outline
business case defines its scope as a 25 year contact involving the
design, build, finance, operation and maintenance of the facility
for circa 35% of the total municipal waste stream from the five
authorities (with each also striving to achieve the 70% recycling
and compost target set by the Welsh Government). He advised of the
aims of the procurement of a long-term contract for the
treatment/disposal of residual municipal waste and detailed the
value for money of economies of scale of the shared procurement
costs (supported by the Welsh Government) which will provide a
solution that reduces the reliance on landfill to a
minimum.
The process aims to seek to deliver the best environmental,
cost effective and practical solution to municipal residual waste
that is left over in each authority after recycling and composting
has been maximised in each area.
Commercial Sensitivity
Reference was made to the commercial sensitivity of the
project and the need for the Panel to determine as to whether, in
view of potentially confidential information that may be disclosed,
the public should be excluded from its meetings. As discussed
earlier in the meeting it was accepted that there would be
occasions when it would be necessary to exclude the public but that
where possible reports would be considered when they are
present.
A query was also raised as to whether the nominated
representatives would be able to divulge information to their
colleagues and it was confirmed that confidential information
received during the course of the meeting should not be discussed
although the minutes of the meeting (excluding such confidential
details) are a public document. Detailed information is also
available on the Prosiect Gwyrdd web site.
Role of Scrutiny
Reference was then made to the governance structure and it
was noted that the partnership is governed by a decision making
Joint Committee, consisting of two Councillors from each
Cabinet/Executive from each authority. The Joint Committee
also governs the project through the 'Competitive Dialogue' process
and the final decision to appoint a contractor will be made by each
Council. The Project Board (with senior advisors from each
authority) advises the Joint Committee with the assistance of the
Project Team and external advisors. The role of
the Joint Scrutiny Committee is to scrutinise the decision making
process. However, there are three key decisions that must be made
by each individual Partner Council - entering into the partnership,
the appointment of a preferred bidder and the final contract
award.
Overall Timeline
Reference was made to the timeline for the procurement
process (invitation, prequalification, outline solutions, detailed
solutions, final tender, preferred bidder) and it was noted that
all bids will be assessed against agreed criteria, involving
environmental impacts, sustainability, service delivery, cost and
value for money. The Partnership is technology neutral and will
look at all technologies that may be proposed for the contract,
although technology was not prescriptive at the initial invitation
stage.
Those who were successful at the pre qualification
questionnaire stage (where their bids were evaluated in accordance
with the pre-set evaluation criteria for the Project) had been
invited to submit outline solutions for the Project, in line with
the Procurement Plan. Prosiect Gwyrdd is currently in the
middle of the competitive dialogue process at the detailed
solutions stages with three separate bidders (there were four but
one has subsequently withdrawn). Each is proposing an energy from
waste facility. Covanta Energy Ltd is proposing a merchant energy
from waste facility located at Brig y Cwm, Merthyr Tydfil, Veolia
ES Aurora Ltd an energy recovery facility located at Bowlease
Common, Newport and Viridor Waste Management Ltd a merchant energy
from waste with combined heat and power facility located at Trident
Park, Cardiff.
This stage of the competitive dialogue process requires
shortlisted participants to further refine their outline solutions
and intimately submit a detailed submission of their
solutions.
Following this detailed stage of the procurement, Prosiect
Gwyrdd has reserved the right to include a ‘refined solution’
stage, if required, for clarification and further discussions with
Participants. Following this stage the successful Participants will
be invited to submit a final tender.
It is anticipated that two participants will remain at that
stage with the preferred bidder being appointed in August with the
contract being finalised by the end of the year.
A query was raised on the number of proposals/technologies
submitted and it was noted that the project is technology neutral
and the procurement stance was to set out the requirements through
a specification and evaluation stage. This was presented to the
market with an invitation to submit proposals that best meet those
needs. It was explained that the pre qualification stage was
evaluated in accordance with the pre-set evaluation criteria for
the Project and the eight highest scoring Companies were invited to
submit outline solutions for the Project, in line with the
procurement. Those that did not score high enough were deselected
and two submissions were non-compliant. At the ISOS stage, the
Project received five outline solutions (from four companies) and
four solutions (from four companies) which were taken through to
the detailed stage (invitation to submit detailed solutions). One
Solution has subsequently withdrawn.
It was raised as to whether, as there are now only three
companies, it would be possible to invite another company to
participate. It was confirmed that under procurement rules it is
not possible to invite a new company.
Action - It was agreed that a presentation
on the selection process be presented at the next meeting.
Risks and Issues
Reference was then made to the risks and issues associated
with the project and it was noted that waste flow calculations are
critical to the success of the Project and that information is made
up of each of the partner’s assumptions and predictions over the
contract term. This will be a critical area for the Joint Scrutiny
Panel to scrutinise.
During the course of the debate reference was made to the
tonnage associated with the bids and the subsequent gate fees
arising therefrom. It was noted that such detail has not yet been
submitted and it would be necessary to calculate the fees once the
information is forthcoming.
The Project has identified that a fundamental risk to any
waste procurement project is the availability of a suitability site
with full planning permission. It was noted that such procurements
do not usually envisage planning permission to be received by
financial close. However one participant has already received
planning permission, another is under consideration and a third is
due to be submitted in the near future.
Mr. Williams also outlined the health and environment
issues, partner affordability and delivery of value for money and
advised that there is also a requirement for the individual
Councils to buy in and sign off the project. With regards to
health and the environment, he advised that any subsequent changes
in legislation would need to be adhered to by the successful
contractor, through a ‘change in law clause’ in the
contract.
Joint Working Agreement
The Panel were reminded that Prosiect Gwyrdd cannot contract
directly with the successful bidder and a lead authority needs to
be selected for this purpose and that the joint working agreement
is currently under review in order to achieve
this.
Reference was made to the existing joint working agreement
which sets out the governance arrangements for the duration of the
procurement process that has been signed by each of the
participating authorities and to the contractual rights and
obligations detailed within that document. It was confirmed
that the decision as to award of contract will be a matter for each
authority, though it was noted that the agreement contains
provision that if the proposed solution meets the output
requirements and is within the affordability envelope then any
partner authority that fails to confirm the appointment of the
Preferred Bidder shall be deemed to have withdrawn from the process
and could potentially be required to compensate the remaining
authorities subject to a liability cap of £3m.
Action- details of the existing joint
working arrangement, and, in the event that not all partner
authorities buy in and sign up to the project the implications
arising therefrom, be presented to the next
meeting.
During the course of the debate reference was made to the
elections in May 2012 and the potential for changes in political
administration. In noting that the tenders would be invited by that
time but that the final report would not be considered by the
partner authorities until the Autumn it was agreed that it would be
necessary to ensure that seminars specific to Prosiect Gwyrdd are
incorporated within the Member induction programme so that they are
fully aware of the context and required outcome of the Project when
they consider the final report.
Actions
1. Seminars
on Prosiect Gwyrdd to be incorporated within the Members induction
programme
2. Prosiect
Gwyrdd Joint Committee to consider whether the timeline needs to be
revised
Member Engagement
It was accepted that at the commencement of the Project it
had been recognised that there was a requirement to undertake
comprehensive stakeholder/community group engagement and this was
achieved through the approved communications strategyand a number
of established consultative mechanisms. Further events have been
scheduled.
As raised earlier in the meeting the complexity of the
commercially sensitive project and the prescriptive procurement
process was seen as an issue for engagement. Members reiterated
that there had been a perceived lack of transparency and much
concern has been raised over the proposed technology and strong
public opposition has been received to the proposed sites (Cardiff,
Newport and Merthyr).
It was confirmed that the decision on the preferred bidder
requires the approval from Council of each of the five partners and
that any views express would need to be taken into consideration at
that time in order that an informed decision can be
taken.
It was accepted that there is a risk to the project if it is
not signed off by the respective Councils and implications for
those partners as detailed in the Joint Working Agreement (and
discussed earlier in the meeting). There would be a need to
identify an alternative waste solution with a new procurement
process, there would be prolonged exposure to both landfill costs
and recycling fines and the loss of Welsh Government grant and the
procurement costs.
Action - minutes of the Prosiect
Gwyrdd Joint Committee to be presented to the Panel
Mr. Williams responded to a number of questions raised over
and above those which were considered during the course of the
presentation and in particular to the matrix scoring for those
companies that originally expressed an interest. Reference was made
to the methodology of how the criteria was applied and the
subsequent matrix scores and whether they were available to be
viewed. It was confirmed that the information has not been
released. Mr. Williams explained how the approved
process had been implemented at pre qualification stage which had
resulted in four being invited to participate in the next stage and
reiterated that eight of the highest scoring companies were invited
to submit outline solutions for the project and those that did not
score high enough were deselected and two submissions were
non-compliant.
It was suggested that in view of the amount of queries
received from the public such information should be made available
in order that the process can be seen to be transparent and there
is an explanation as to how a company had either progressed to the
next stage or had been disregarded. In noting that many
enquires relate specifically to technology, it was confirmed that
thepre qualification stage did not evaluate technology.
Action- presentation to be made to the next
meeting detailing the selection process, and, if possible,
information on the specific matrix scores.
The Project Team were thanked for their informative
presentation and responding to questions and issues raised by
members.
Action -copy of the presentation, with any
confidential information redacted, to be sent to the
Panel.
Correspondence received from Councillor B. Bright
(Cardiff City Council)
The Panel were circulated with a copy of a statement
received from Councillor B. Bright, Newport City Council, which
advised that its Labour Group is vehemently opposed to any of the
waste incineration options on the current Prosiect Gwyrdd
shortlist, and particularly to the one at Bowlease Common. It also
raised a number of questions to which he requested a
response.
Action- It was agreed that responses to the queries would be
collated and sent to Councillor Bright. A copy of the
response would be copied to the Panel.
Correspondence received from Rod
Walters
The Panel were circulated with a copy of an email from Rod
Walters seeking responses to a number of questions that he
raised.
Action - It was agreed that responses to
the queries would be collated and sent to Mr. Walters and that copy
of the response would be copied to the
Panel.
The meeting closed at 12.30pm.
--------------
7th October 2011
Present:
Councillor C. J. Williams - Chairman (Vale of Glamorgan
Council)
Councillors:
Councillors M. G. Parker and D.V. Poole (Caerphilly County
Borough Council)
Councillor R. McKerlich (Cardiff County Council)
Councillor Ms. V. Smith (Monmouthshire County
Council)
Councillors B. Bright and S. Jones (Newport City
Council)
Councillor Mrs. M. Kelly-Owen (Vale of Glamorgan
Council)
Together with:
J. Rogers, J. Jones and C. Forbes-Thompson (Caerphilly
County Borough Council), P. Keeping (Cardiff County Council), H.
Ilett (Monmouthshire County Council), D. Collins (Newport City
Council), J. Wyatt (Vale of Glamorgan Council)
Prosiect Gwyrdd Officers:
M. Williams (Project Director), I. Lloyd-Davies
(Communications Officer) and M. Falconer (Finance
Manager).
1.
APOLOGIES FOR ABSENCE
Apologies for absence were received from D. Perkins
(Caerphilly County Borough Council), M. Williams (Caerphilly County
Borough Council), R. Quick (Vale of Glamorgan), Councillors S.
Wakefield (Cardiff County Council) and S. Howarth (Monmouthshire
County Council)
2.
DECLARATIONS OF INTEREST
There were no declarations of interest received at the
commencement or during the course of the meeting.
3.
MINUTES - 22nd JULY 2011
It was agreed that the minutes of the meeting held on
22ND July 2011 be approved as a correct record.
4.
EXEMPT MATTER
Members considered the public interest test certificate from
the Proper Officer and concluded that on balance the public
interest in maintaining the exemption outweighed the public
interest in disclosing the information and it was
RESOLVED that in accordance with Section 100A(4) of the
Local Government Act 1972 the public be excluded from the remainder
of the meeting because of the likely disclosure to them of exempt
information as identified in paragraph 14 of Part 4 of Schedule 12A
of the Local Government Act 1972.
PRESENTATION SHORTLISTING PROCESS
Mr M Williams (Prosiect Gwyrdd) gave a presentation to
explain the shortlisting process. At the previous meeting there was
debate on the procurement process and how it arose that all three
final bids are all energy from waste (EfW) proposals.
Pre-Qualification Questionnaire
Mr Williams explained the procurement process started with
the initial invitations to potential interested parties. The
Pre-Qualification Questionnaire (PQQ) followed this and ensured
that only those financially and technically able to provide the
service would go forward to the next stage. In order to evaluate
the PQQ’s an evaluation matrix was devised and consisted of 12
criterions that included, general company information, eligibility
(legally entitled to participate), technical capacity and ability,
environmental and quality management and financial and economic
standing. In total 47 interested parties expressed initial interest
and 36 downloaded the PQQ. There were 14 PQQ’ s returned and of
these 2 were immediately rejected because they did not meet the
criteria and a further 2 were rejected when they failed to complete
the eligibility and certification form. This left ten potential
bidders with the top 8 were taken through to the next
stage.
Competitive Dialogue
The commencement of competitive dialogue started in May 2010
with the aim to find the most economically advantageous tender that
best meets the Partnership requirements and is in line with EU
procurement rules. The Invitation to Submit and Outline Solution
(ISOS) asked the top 8 to submit outline solutions. The Project
Board and the Joint Committee approved the methodology for the
ISOS, which gave each bidder the opportunity to submit 2 solutions,
which were not limited in terms of the type of solution. The aim
was to select the four highest scoring solutions. This resulted in
four bidders submitting five solutions; all five were EfW, with one
bidder submitting two EfW at two different sites. The lowest
scoring solution was de-selected.
Four companies were invited to the ‘Invitation to Submit a
Detailed Solution’ (ISDS) stage and in March 2011 one company
withdrew its submission. The remaining companies are at different
stages of the planning process.
Energy From Waste
Mr Williams outlined the background to the final bidders all
submitting EfW solutions. He stated that in England the majority of
solutions have been EfW. There have been 42 residual waste projects
in England and 29 are EfW. There were 8 Mechanical Biological
Treatment (MBT) to fuel solutions, however the fuel output has
either gone into EfW, Gasification or been exported to Europe. A
further 4 are also MBT but with a landfill output, the result is
compost like output that has a limited use that cannot be used on
land for food production or animal grazing. There was 1 autoclave
solution, which involves the steam cleaning under pressure of the
residual waste, the process can vary but there is no sustainable
market for the output. The result is a product that cannot go to
landfill because it is still organic, and will most likely go to a
Gasifier or EfW.
Evidence if
Bias
Mr Williams looked at the procurement process to see if
there was any evidence of bias towards an EfW solution. He stated
that there was a Stakeholder (Member) Evaluation workshop in
September 2009, and a Scrutiny Workshop on the evaluation
methodology in December 2009. The technology neutrality was tested
with the Joint Committee in January 2010 when they were asked if
they saw any bias towards EfW. In February 2010 the technical
advisors were also asked if they was any bias towards EfW and they
confirmed there was none.
Mr Williams stated that he could see no real bias in the
procurement process however there may have been some influence
towards EfW from the following:
Reference Project
Mr Williams stated that the outline business case (OBC)
required a reference project to be developed. This allows a
financial assessment to be carried out. The reference project
chosen was EfW and it is possible that the market may have
interpreted that this was what was required. Councillors asked why
EfW was chosen and it was explained that various technologies were
assessed against a number of criteria and it was not intended to be
a signal to the market. The Project Board and individual local
authorities approved the reference project and Welsh Government
(WG) approved the Business Case. It was widely communicated that
the reference project was only a model for the business case and
the project was open to any technology that met the Partnership’s
published requirements.
Landfill Diversion Authority
Requirement
Mr Williams stated that because of this existing requirement
upon local authorities any solution from bidders that offered a
landfill option would not do well. This would impact negatively
upon any MBT solutions that have a landfill output.
Extra Recycling Authority
Requirement
This requirement would normally favour alternative
technologies, however WG have allowed bottom ash as ‘recycling’,
which may neutralise this benefit or in some cases favour EfW
technologies.
Most Economically Advantageous
Tender
This is defined by the evaluation criteria and has a cost
element. EfW is often less expensive.
Alternative Technologies
Alternative technology solutions have been prominent in
local authority waste projects when local authorities have
communicated anti-incinerator policies to the market. But in
situations where there is no such policy EFW will often be
successful.
Members suggested that technological solutions that have
moved on since the procurement process commenced and health
considerations should have a higher weighting. It was proposed that
in view of the withdrawal of one of the final 4 bidders that
consideration is given to allowing an alternative newer technology
to take the place on a ‘wildcard’ basis. Mr Williams stated that
all technologies have some element of burn of the end
product.
Mr Williams discussed reasons why alternative technologies
could not be sought and introduced at this stage of the procurement
process. He stated that fundamental principles of procurement
require equal treatment, transparency and non-discrimination. If
the Partners wanted to seek alternative technologies at this stage
the procurement process would have to stop and start again from the
beginning.
5.
GATE FEE MODEL AND GAIN SHARE
Mr M Falconer (Prosiect Gwyrdd) gave a presentation to
outline a generic financial model for the successful contractor
over the facility operating period. The model covers Cost, Income
and Contractors Profits. The typical costs include repayment of
debt incurred in building the facility at 45% and operational costs
at 55%. Income includes the Prosiect Gwyrdd (PG) gate fee that
covers a guaranteed minimum payment. It would also include third
party waste, from other local authority gate fees and commercial
and industrial gate fees, as well as electricity /energy income
from treating both sources of waste.
Members asked if there is a restriction preventing the
successful bidder from offering lower gate fees to other customers.
Mr Falconer stated that this issue in relation to Other Local
Authority Gate fees had been discussed in dialogue with a
favourable response although the exact details had not yet been
agreed. Restrictions on other Third Party gate fees may inhibit the
bidders commercial flexibility and may not be a valid comparison
when factors such as different contract lengths, Welsh Government
grant, etc are considered.
The bidders are all proposing plants with capacity in excess
of PG requirements, with capacity varying from 256,000 to 750,000
tonnes per annum. In these cases Third Party Income and Electricity
Income are much more significant then if the facility was sized for
Prosiect Gwyrdd needs.
The gate fee is set on the basis of the contractor’s model,
which assumes the plant will operate to capacity. They will also
make an assessment of the availability of third party tonnage, the
market rate for commercial and industrial waste (C&I) and other
municipal solid waste (MSW). The electricity income is another
factor in their modelling and PG waste fills the gap to achieve the
contractors target rate of return.
Risks
The risks to the project were outlined in that the
Contractor will bear the risk of any shortfall in third party
income both from reduced tonnage and from reductions in expected
gate fee. PG would take the risk of not meeting its guaranteed
minimum tonnage (GMT). Members discussed the risks should a
contractor fail and go bankrupt. Mr Williams stated that
termination provisions are set out in the contract and in some
cases PG can step in to run the plant.
Pro-rata
The pro-rata concept was explained in that PG would only pay
for its share of the facility for any ‘oversized’ facility. Members
asked how the figures are calculated and it was explained that the
normal approach is to apportion based on PG tonnage relative to the
total capacity of the facility.
6.
FORWARD WORK PROGRAMME
Mr J Jones stated that he had liaised with Mr Mike Williams
(PG) to develop a draft forward work programme that is linked to
the key deliverables of the PG project. It is proposed that
meetings are arranged as follows:
- November 2011 - The joint working agreement
- December 2011 – Shortlisting of final 2 bidders.
- January 2012 – call for evidence invitation to key
stakeholders.
- (Date to be determined) – to consider final joint working
agreement.
It was agreed that there should be careful consideration of
the key stakeholders to be invited to the meeting in January 2012.
Suggestions included an Expert Witness who has received peer
validation of their work, Friends of the Earth, Welsh Chief Medical
Officer, the Environment Agency and an Industry Representative (to
give a balanced view). It was agreed to discuss this at the next
meeting.
Action: Agenda for next meeting to include
stakeholders to be invited for January 2012 meeting.
Mr Jones asked Members to consider changing the day of
future meetings, as Fridays are difficult for the PG Legal Officer.
It was agreed to change the day to Monday afternoons, Mr Jones to
change the dates suggested in the forward work programme
accordingly.
Action:Dates for future meeting to be
amended.
7.
MEMBER ENGAGEMENT
Mr Mike Williams (PG) stated that PG Project Team are keen
to obtain feedback from Members and asked for suggestions on how
future awareness raising could take place. Members suggested
attending Council meetings at local authorities and writing to
group leaders and including information in induction pack for
Members after the May 2012 elections. Given the importance of this
issue, it was suggested that a further session on member engagement
be held at a future meeting.
8.
TO RECEIVE AND NOTE THE INFORMATION ITEMS
The minutes of the Project Gwyrdd Joint Committee held on 21
March 2011 and 18 July 2011 were noted.
9.
ANY OTHER BUSINESS
Mr Mike Williams stated that at the last meeting of the
Joint Committee the issue of site visits by the Joint Scrutiny
Panel was discussed. The Joint Committee did not feel it was their
role to say yes or no and the joint scrutiny panel should
decide.
Meeting closed at 12:48pm.
--------------
During consideration of the minutes Members
reiterated their request for an update on the recent new recycling
arrangements that had been put in place and also for an update on
recycling incentives. A number of Members also requested that
consideration be given as to how recycling facilities can be
addressed at premises of multiple occupancy e.g. blocks of flats
and that both the Housing and Planning departments be reminded of
the need to address waste management issues when considering
applications / issues in their service areas.
It was subsequently
RECOMMENDED - T H A T the minutes of the
Prosiect Gwyrdd Joint Scrutiny Panel be noted and that further
reports as detailed above be presented to the Scrutiny Committee in
due course.
Reason for recommendation
In order that Members can consider the
progress being made in relation to the current recycling regime and
other initiatives.