Agenda Item No
The Vale of Glamorgan Council
Scrutiny Committee (Economy and Environment): 27th May,
2009
Report of the Director of Environmental and Economic
Regeneration
Prosiect Gwyrdd - A Regional Partnership for the Procurement of
a Residual Waste Treatment Solution
Purpose of the Report
1.
To seek approval to participate in partnership with the other
Prosiect Gwyrdd Partners to seek the procurement of a future
residual waste treatment solution for all residual waste that can
not be reused, recycled or composted.
2.
It should be noted that while the following recommendations within
this report are common to all the reports being taking to the five
individual Prosiect Gwyrdd authorities and are worded to reflect
full approval of Committee are only being asked to support these
recommendations at this time.
Recommendations
1.
To agree that the three conditions, (as set out in Appendix A) of
the report dated 17th December that approved the Outline Business
Case ('OBC') for Prosiect Gwyrdd that those conditions have been
satisfied
2.
To approve the ‘OBC Health Check Addendum 2009’ appended at
Appendix B to this report that represents the revised outline
business case for Prosiect Gwyrdd.
3.
Approves the proposed strategic approach to procurement for
Prosiect Gwyrdd which includes:-
(I) proposals to develop the evaluation
criteria and weightings that will be a matter for the joint
committee to determine following stakeholder consultation;
(ii) is premised upon a publicly owned site
being made available to bidders (note well that this does not
preclude bidders putting forward proposals based at other
locations/sites within their control ) and that the site proposed
is known as Tatton Road, Newport. This recommendation being
subject to:
· Newport City Council agreeing to
the same.
· All five
authorities agreeing to the terms and conditions pursuant to
which such site is to be acquired or an option secured, which terms
will address, how the same is to be financed by the five
authorities and what is to happen at the end of the project
life.
4.
Approves the procurement costs as provided in paragraphs 62 to 68
of Appendix A - Common Report) to Preferred Bidder stage for the
Project.
5.
Approves that the Council proceed with the procurement on the basis
of affordability range contained in appendix G and agree that the
financing options set out in paragraphs B are approved
6.
To approve that the Council enters into a Joint working Agreement
(JWA1) with the other authorities, in the form set out in appendix
D to this report and that pursuant thereto and amongst other things
:
(a) a Joint Committee, with the delegated authority
set out in the JWA1 be established and that the Cabinet Members
with responsibility for the time being for waste management and
financial matters be appointed to represent this authority on the
Joint Committee (and in his or her absence the Cabinet Members with
responsibility for the time being for waste management and
financial matters be entitled to act in such capacity);
(b) Subject to Cardiff Council agreeing the same,
that Cardiff Council will act and shall have full authority to act
on behalf of all the authorities as Lead Authority for the
procurement process;
(c) that the decision as to award of contract will
be a matter for each authority, though it should be noted that the
JWA contains provision that if the proposed solution meets the
output requirements and is within the Affordability Envelope then
damages will be payable should an authority withdraw from the
procurement process or determine not to award a contract, with such
damages being capped at £3,000,000;
(d) a Project Board comprising of officers from
each authority will be established with the delegated authority set
out in the JWA1.
7.
That stakeholder consultation on the Project is carried out in
accordance with the approach set out in appendix OBC Health Check
Addendum, Appendix B.
8.
To approve that the procurement for Project Gwyrdd be commenced
subject to :
(a) JWA 1 being concluded by all authorities;
(b) the matters set out in recommendation 3 (ii) is
agreed by all authorities; and
(c) Cabinet receiving confirmation from WAG that
the WPPO Scrutiny panel is satisfied that the terms and conditions
of the funding package (see WAG letter dated 30.3.09 appended to
this report as OBC Health Check Addendum, appendix B.) have been
met prior to posting OJEU Notice.
9.
The matter be reported back to Council when decision is sought to
award the contract or before hand if the Joint Committee wishes to
refer any matter back to Council.
10. That this report be
referred to the Corporate Resources Scrutiny Committee for
approval.
11. To approve the final
commitment that will be required to achieve the recycling and
composting levels approaching 65%.
12. That this report and
any comments received from the Economy and Environment and
Corporate Resources Committees be referred to Cabinet and then Full
Council for approval.
Reasons for the Recommendations
1.
To confirm compliance with the requirements of Minute No C269
resolved by Cabinet on the 17th December, 2008.
2.
To ensure that Cabinet/Committee are satisfied that the OBC Health
Check represent the revised outline business case for Prosiect
Gwyrdd.
3.
That the proposed Procurement Strategy and land actuations
proposals are accepted.
4.
That the equal sharing of procurement costs is acceptable.
5.
That procurement is carried out where it is consistent with the OBC
affordability range and finance options.
6.
That the Joint Working Agreement (JWA1) is acceptable and jointly
entered into with the other Prosiect Gwyrdd local authorities.
With the setting up of a Joint Committee, lead procurement
authority and compensation clauses for any partner authority
deciding to not more to award of contract at the end of the
procurement process.
7.
That appropriate Stakeholder Consultation is carried out.
8.
That subject to the specified conditions that the procurement of a
residual treatment solution for the Prosiect Gwyrdd local
authorities is commenced.
9.
That a further report be brought to Council following or during the
procurement process in order to consider Award of Contract.
10. To ensure
consideration of the report details by the appropriate Scrutiny
Committee.
11. To ensure that
sufficient resources are available to meet WAG's future recycling
and composting targets.
12. To obtain an
Executive and Full Council decision, to enable this Council's
involvement in the project to continue.
Background
3.
Cabinet on the 17th December, 2008 resolved that the collaborative
partners forming Prosiect Gwyrdd (minute C269 refers):
RESOLVED -
(1) T H A T the final draft OBC be approved
for submission to WAG based upon the affordability gap described
within the report for a Residual Waste Treatment Solution
predicated upon a technology neutral assumption.
(2) T H A T the approved OBC would remain
valid subject to the following three conditions:
(i) The Procurement being premised upon a
publicly owned site being made available to bidders and as such
maintaining discussions with WAG was necessary until a public
authority contractually committed to securing an option in the
Partnership's control but that it be noted that this would not
preclude a privately owned site being brought forward by a bidder.
(ii) WAG providing sufficient comfort that
they fund the partnership to at least a minimum level of funding
over the life of Prosiect Gwyrdd as per the OBC and that its
decision be made prior to 31st March, 2009.
(iii) The other partner authorities also
approving the OBC with the same conditions applying.
(3) T H A T, if any of the three conditions
in Resolution (2) above were not all met by 31st March, 2009,
Cabinet approval for OBC would automatically lapse and the Vale of
Glamorgan Council would consider alternative options for residual
waste treatment outside the scope of Prosiect Gwyrdd.
(4) T H A T the Director of Environment and
Economic Regeneration in consultation with the Director of Legal,
Public Protection and Housing Services and Cabinet Members for
Visible and Building Services and Legal and Public Protection be
authorised to extend existing Memorandum of Understanding between
partnership Councils to 31st March, 2009 to facilitate further
joint working arrangements pre-procurement.
(5) T H A T if the conditions in Resolution
(2) above were met, a further report would be submitted to Cabinet
for recommendation to the Council to seek a full decision in
respect of Prosiect Gwyrdd including:
|
·
the final affordability envelope
|
|
·
the proposed governance arrangements and formation of a Joint
Committee
|
|
·
the lead Authority for procurement
|
|
·
the final Joint working Agreement and
|
|
·
evaluation criteria for the procurement process
|
(6) T H A T a full Stakeholder Consultation
Strategy be further developed including the launch of the Prosiect
Gwyrdd Website.
(7) T H A T the re-establishment of the
previous joint trans-boundary Scrutiny Committee arrangements be
re-established.
Reasons for decisions
(1) To allow the OBC to be submitted to WAG
as a basis for financial support for Prosiect Gwyrdd to reduce the
affordability gap.
(2) That Cabinet approval is conditional on
WAG meeting all the conditions needed to comply with the OBC.
(3) That WAG is aware that Prosiect Gwyrdd
will end should they fail to confirm funding support by 31st March,
2009.
(4) To allow the existing Memorandum of
Understanding to be extended as required to allow continual
partnership working.
(5) To obtain the necessary authority to
progress the procurement stage of the project.
(6) To ensure full stakeholder
consultation.
(7) To allow the Scrutiny Committee (Economy
and Environment) to continue its previous work in respect of the
procurement process.
4.
This report addresses a number of these recommendations and seeks
endorsement of a procurement strategy to pursue a residual
treatment option. It also addresses the outline contract
specification, optional site acquisition and affordability
position. The report is being submitted to all 5 partnering
authorities over the next few months with all individual reports
based on the full Common Report 2 which is attached for
consideration as Appendix 1 to this report. It is recommended
Members consider the full common report that provides a more
detailed description of the relevant issues.
Relevant Issues and Options
5.
The Authority is presently fully committed to the Prosiect Gwyrdd
Partnership and is not considering any other option for future
residual waste treatment. Our current contract with Biffa
Waste Services for landfilling residual waste will terminate in
2018 and it is unlikely that there will be any appropriate
alternative to Prosiect Gwyrdd that will provide further disposal
provision after this date. Prosiect Gwyrdd has taken three
years to reach the procurement stage and is likely to take a
further 5 to 6 years before any solution is operational.
Officers are of the belief that no other procurement option
will deliver a successful outcome before 2018.
6.
Prosiect Gwyrdd is a path finder project in Wales for the Wales
Assembly Government (WAG) Residual Waste Treatment Procurement
Programme and supports the 'Making the Connections Agenda' showing
clear economies of scale and joint working benefits. It's
size is increasingly attractive to the market and should result in
reduced gates fees over smaller or single authority procurement
options.
7.
WAG has made it clear through its future strategic direction papers
that resources are expected to be directed towards local
authority policies which are based on very high levels of recycling
and composting. The most recent paper (Towards Zero Waste,
April 2009,) proposed specific targets that are expected to be
adopted and also, it is anticipated, will be given statutory
backing. These are set out below:
· 2009/10 - 40% (of
which 15% is composting, not food specific)
· 2012/13 - 52% (of
which 12% is a food specific target)
· 2015/16 - 58% (of
which 14% is a food specific target)
· 2019/20 - 64% (of
which 16% is a food specific target)
· 2024/25 - 70% (of
which 16% is a food specific target)
· Maximum amount of
residual waste of 150kg per household per annum by 2024/25
· Reduce the amount
sent to landfill to 10% by 2019/20
· Reduce amount sent
to landfill to 5% by 2024/25
· Maximum amount of
MSW subject to EfW of 30% (tapered from 42%).
8.
The revised waste strategy for Wales published on the 29 April,
2009 for public consultation is consistent with the emerging
National Waste Strategy and is a condition of future WAG funding.
Given the direction of travel that has been set out not only
is Prosiect Gwyrdd compliant with future policy, but well placed
for any funding allocations.
9.
While the Prosiect Gwyrdd procurement process will be technology
neutral, with the final solution being determined during the
Competitive Dialogue stages, it is likely that some of the bidder
solutions proposed will entail a thermal treatment component.
Any proposal of this nature will require heat plan
submission. The competitive dialogue process will allow
consideration of all available and emerging technologies that meet
the output specification requirements. This will fully allow
a range of possible solutions to be considered and evaluated.
The Outline Business Case (OBC) has been considered from a
technology neutral starting point and the procurement will continue
to be conducted on the same basis.
10. The strategy for
procurement sets out all of the key principles for the Project and
the strategic elements contained in this report. The draft
procurement plan sets out how the procurement is expected to be
delivered. The key matters that will drive out the final
delivered solution are set out in the Output Specification.
The Outputs prescribe:
· The level of
biodegradable diversion, and the level of recycling to be
achieved
· Securing and
maintaining markets for all products and by-products from the
facility
· The level of
Facility Design service we require, how that the facility will be
delivered and the works involved
· Climate Change and
Emissions Standards
· Environmental
Consideration and Nuisance Control during construction and
operation
· Environmental
Management of the operational phase including
· Waste types and
delivery controls
· Public facilities
(such as visitor centres) and
· Continued
Stakeholder Engagement requirements during delivery and
operations
· Social and
Corporate Responsibility.
11. The procurement phase
is just over 24 months from placing of the OJEU notice to the
selection of the preferred bidder and that is believed to be
adequate to complete the competitive dialogue process. In summary,
the indicative timetable is therefore as follows:
Activity
|
Financial Year
|
|
Submit OBC to WAG
|
Winter
|
2008/09
|
|
Conditions met
|
Spring
|
2009/10
|
|
WAG Approve the O~BC and Funding
|
Spring
|
2009/10
|
|
Decision to proceed
|
Summer
|
2009/10
|
|
Place OJEU
|
Autumn
|
2009/10
|
|
Commence competitive Dialogue
|
Winter
|
2009/10
|
|
Select Preferred Bidder (Full Council Report)
|
Autumn
|
2011/12
|
|
Planning Starts
|
Autumn
|
2011/12
|
|
Contract Close
|
Spring
|
2012/13
|
|
Construction Starts
|
Autumn
|
2012/13
|
|
Gates Open
|
Autumn
|
2015/16
|
A full master project timetable is included in the
OBC Health Check Addendum 2009 contained in Appendix B of Appendix
1.
12. The Project has
identified that a fundamental risk to any waste procurement project
is the availability of a suitable site that has a reasonable
opportunity for obtaining full planning permission. The
preferred approach for all waste procurement projects, in line with
national guidance, is for the relevant local authority(s) to
acquire sites in line with the adopted Development Plan and/or the
relevant Regional Waste Plan or where they are confident the
proposal will accord with a development plan currently in
preparation. This way the Project will maximise the
competitive potential during the tendering process by providing
interested parties with a potentially suitable location upon which
to base their solutions. As such the Partnership is seeking
to bring forward an Optional Site within local authority
control.
13. It should be noted
that this approach does not prevent bidders putting forward other
sites under their control as part of their bid. Bidders could
evaluate the Optional Site against any other site they consider
they have access to, and formulate their solutions
accordingly. The Project evaluation methodology would
ultimately judge the merits of each proposed solution during the
evaluation stages of the procurement.
14. While a procurement
of this nature will have significant risks, the main risk aspects
anticipated are: financial, regulatory, procurement, design,
political, planning, construction and commissioning, operational
and environmental. The key financial and legal risks are
discussed in subsequent sections, the other key project risks that
remain high are:
· A failure to
obtain planning and permitting permissions (either on the Optional
Site or any other site(s) proposed by potential preferred
bidder;
· Financial climate
worsens and the funding strategy fails;
· Significant
timetable delays;
· Managing risk
throughout the project is key to robust delivery of the Project’s
benefits, therefore updating mitigation strategies and
identification of new risk will continue throughout.
Resource Implications (Financial and Employment)
15. The procurement
decisions, while overseen by the Joint Committee, will be taken
forward by an officer Project Board as detailed in Schedule 1 of
the JWA1 provided as Appendix D of Appendix 1, with a fully
resourced Project Team working to deliver the complex procurement
stages. With the lead authority governance model, once the
waste management contract has reached financial close, the benefits
and obligations of the contract will be passed back by the Lead
Authority to the other four authorities. Issues around
the risk of these arrangements (the Lead Authority role) are dealt
with under legal implications.
16. Central to the
development of the affordability model is an assumption that the
WAG would provide financial support to Prosiect Gwyrdd. Prosiect
Gwyrdd received formal notification from WAG on 30 March, 2009
(letter provided in Appendix B) of the terms under which they will
be providing funding to joint working Local Authority residual
waste treatment projects in Wales. The letter confirmed that
WAG would provide support based on 25% of the Shadow Tariff's
projected Gate Fee for the project and instructed the Partnership
to complete its "OBC Health Check" review and present it with
updated cost projections for the project based on its terms and
conditions.
17. The outcome of the
Partnership's OBC Health Check review and modelling of the WAG's
funding terms and conditions has been to increase the funding
ceiling for the project from the estimated £7.8 million per annum
to a ‘maximum’ ceiling of £9.124 million per annum. The table
below explains the reasons for the increased funding:
Table 1.0 Increased WAG Funding Profile
|
WAG Funding Contribution
|
Increase
|
Rationale
|
|
£7.8 million p.a.
|
|
Approved OBC 2008 estimate
|
|
|
+ £0.42 million
|
Increase in % of gate fee funded by WAG from
23.77% to 25%, in line with WAG funding conditions for all
projects
|
|
|
+ £0.49 million
|
9 month timetable slippage caused by WAG
policy decision delays
|
|
|
+ £0.41million
|
Increased bank funding costs due to the
"credit crunch" and economic downturn
|
|
£9.124 million p.a.
|
|
April 2009 WAG funding award
|
18. The JWA1 is attached
as Appendix D of Appendix 1 and Table 2.0 below outlines each
partner’s Revenue contribution over this phase of the
procurement.
Table 2.0 – Net Revenue Costs to Preferred Bidder
stage
|
|
2009-10
(part-year from OJEU)
|
2010-11
|
2011-12
(11 months)
|
Total (to
Preferred Bidder stage)
|
|
Procurement Cost Schedule
|
371,538
|
772,351
|
775,816
|
*1,919,705
|
|
Other Project Costs
|
221,175
|
56,375
|
42,025
|
319,575
|
|
|
|
|
|
|
|
Project Total
|
592,713
|
828,726
|
817,841
|
2,239,280
|
|
|
|
|
|
|
|
Partner total (Equal share)
|
118,543
|
165,745
|
163,568
|
447,856
|
NB: Procurement costs are net of £415,086 grant
approved by WAG from their Regional Capital Access Fund.
19. In addition to
meeting the revenue costs of the procurement, the Optional Site
requirement to make available to the market a site within public
control or ownership may incur additional costs to the partnership.
The cost of the three year option is £25,000 per annum, if
the option is necessary to exercise then there are two choices: one
of a Freehold Purchase, valued at today’s price of £1,500,000 plus
overage or one of a Lease Rental at £25,000 per acre per
annum. If the asset is managed directly as a Freehold
Purchase the costs would need to be divided on a tonnage basis and
the Council would by liable for approximately 15% of that cost.
20. An Affordability
Analysis has been completed which focuses on assessing the gap
between the Partnership's combined and individual Council's current
budgets and the cost of the 'Reference Project with High Recycling'
("Reference Project") and ‘Landfill with High Recycling’
("Landfill") options. Both options assume delivery of 65% of
each Council’s recycling and composting of their MSW outside of the
scope of the Project. The results are presented graphically
for the partnership in Appendix F of Appendix 1 and for this
Authority at Appendix 2. The "Budget Gap" is the difference
between the current (2009-10) budgets increased by RPI and the
"Landfill with High Recycling” option.
21. It should be noted
that the “Landfill with High Recycling" option is not viewed as a
‘real’ option because of the need to meet landfill diversion
targets and the limited amount of landfill capacity available
locally over the medium term. The option has been included as
a ‘benchmark’ against which the cost of the Reference Project with
High Recycling can be compared.
22. The "Affordability
Gap" is the gap between current budgets and the cost of the
"Reference Project with High Recycling’. Each partner has
arrived at an "Affordability Envelope" which is the projected cost
of the "Reference Project with High Recycling" plus a % based on
sensitivity analysis undertaken as part of the modelling. It
is this affordability envelope (attached as Appendix G) that
Members are being asked to commit to fund. (Full details of
the Affordability Modelling are included within Appendix 1.)
23. Project costs have
been evaluated over a period of just under 32 years representing
the assumed time required to procure, obtain planning consent and
deliver construction, plus the anticipated 25 year contract.
In order to aid comparison all cash-flows have also been
discounted to produce a Net Present Value ("NPV") as at April 2008
prices.
Table 3.0 – Total Partnership and Council Results*
NPV results are based on April 2008.
|
|
Partnership Results
|
Council Results
|
|
|
Total Nominal Costs
£ Million
|
Total NPV
as at April 2008
£ Million
|
Total Nominal Costs
£ Million
|
Total NPV
as at April 2008
£ Million
|
2016/17
Nominal
(1st full yr)
of operation
£ Million
|
|
Partnership Budget
(indexed from 2008/09)
|
640
|
257
|
100
|
40
|
2.5
|
|
|
|
|
|
|
|
|
Landfill with High Recycling ("Do
Minimum")
|
1,274
|
461
|
189
|
69
|
3.7
|
|
|
|
|
|
|
|
|
Reference Project with High Recycling (net of
WAG Funding Support)
|
1,064
|
406
|
156
|
60
|
3.8
|
|
Comparison of Reference Project to Do
Minimum
|
(210)
|
(55)
|
(33)
|
(9)
|
0.1
|
|
|
|
|
|
|
|
|
Budget Gap
|
634
|
204
|
89
|
29
|
1.2
|
|
Affordability Gap
|
424
|
149
|
56
|
20
|
1.3
|
*(Following completion of the OBC Health-Check
2009)
24. For this Authority,
the Reference Project with High Recycling option has the lowest
expected cost both in nominal terms (£156 million, net of WAG
funding) and in Net Present Value terms (£60 million). This
results in a saving of £33 million in nominal terms and £9 million
in NPV terms when compared to the ‘Landfill with High Recycling’
option. This Authority's Budget when compared against the
‘Landfill with High Recycling’ option results in a Budget Gap of
some £89 million in nominal terms. The resultant
Affordability Gap (Reference Project with High Recycling compared
to budget) is £56 million in nominal terms. This report
therefore asks Members to sign up to the cost of undertaking the
reference project plus an agreed % which is detailed in Appendix
G.
25. While the Legal
Implications of this report provides detailed advice on the Joint
Working Agreement (JWA1), Appendix D of Appendix 1, which is
seeking approval as part of this report. The JWA1 does sets
out the following financial issues:
· Clause 7 sets the
Financial Commitment of the Councils, including the making
available to the project sufficient internal resources;
· Clause 10 the
potential liability arising on withdrawal from the project;
· Schedule 5A the
projected costs of the Procurement;
· Schedule 5B Other
Project related costs including cost of the site;
· Schedule 6 the
defined Accounting periods;
· Schedule 7 the
basis of the Liability Report.
26. In essence, the JWA
sets out the cost sharing arrangements, anticipated partner
contributions and the liabilities that may arise should a partner
wish to withdraw from the procurement at any point. In
particular, the document outlines the methodology for determining
the level of compensation payable should a partner wish to withdraw
from the procurement, whilst the estimated cost of the project
remains within the agreed Affordability Envelope (as set-out in
Appendix G).
27. In addition to the
affordability modelling undertaken for Prosiect Gwyrdd which covers
35% of the waste stream an estimate has been calculated of the
costs of treating the remainder of the waste outside of the scope
of Prosiect Gwyrdd.
28. Two scenarios have
been calculated, the first which calculates the cost of achieving
65% recycling and the second calculates the cost of achieving 58%
recycling and sending the remaining 7% to landfill.
29. The current rate of
recycling for this Authority is approximately 40% therefore the
challenge of reaching levels of recycling of 65% cannot be
underestimated. It is projected that over the same 32 year time
period that has been used for the Prosiect Gwyrdd modelling that
there is a budget gap of £25million in NPV terms and £80m in
nominal terms to reach levels of 65% recycling.
30. To only reach levels
of 58% recycling and sending the remaining 7% to landfill it is
estimated that the budget gap would increase to £28million in NPV
terms and £90m in nominal terms. The results are higher than those
to reach 65% recycling due to the ever increasing cost of disposing
waste at landfill.
31. The table below
combines the cost of Prosiect Gwyrdd with the cost of treating the
remainder of the waste to arrive at an overall budget gap for 100%
of this Authority's waste. (Whole System Costing)
Table 4.0 Budget Shortfall Calculations For 100% of
Waste Arisings
|
|
58% Recycling & 42% Landfill (£
million)
|
58% Recycling, 7% landfill & 35% Reference
Project (£ Million)
|
65% Recycling & 35% Landfill (£
million)
|
65% Recycling & 35% Reference project (£
million)
|
|
Prosiect Gwyrdd budget shortfall (35% of
residual waste) - NPV terms
|
34
|
21
|
29
|
20
|
|
Budget shortfall - remaining waste - NPV
terms
|
28
|
28
|
25
|
25
|
|
|
|
|
|
|
|
Total Shortfall - NPV terms
|
62
|
49
|
54
|
45
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Prosiect Gwyrdd budget shortfall (35% of
residual waste) - Nominal terms
|
108
|
59
|
89
|
56
|
|
Budget shortfall - remaining waste - Nominal
terms
|
90
|
90
|
80
|
80
|
|
|
|
|
|
|
|
Total Shortfall - Nominal Terms
|
198
|
149
|
169
|
136
|
|
|
|
|
|
|
32. It can be seen from
the table above that the budget shortfalls are ranked from lowest
to highest as below:
a) The lowest budget gap is projected if the
Authority achieves 65% recycling and proceeds with Prosiect
Gwyrdd. If achieved the Authority would be insulated almost
entirely from the increase in landfill disposal cost and landfill
tax.
b) The next lowest result occurs if only 58%
recycling is achieved and the Authority proceeds with Prosiect
Gwyrdd. The reason for this is that as only 7% of waste is
going to landfill the Authority is being protected from ever
increasing costs of disposing of waste at landfill.
c) The budget gap for 65% recycling and 35%
to landfill is the next lowest. This is due to there being
less insulation to the increasing costs of landfill and the cost of
LAS fines of £200 per tonne are £1million higher in nominal terms
than in the 2 options above
d) The budget gap for 58% recycling and 42%
to landfill is the greatest. Under this scenario LAS fines
are £12million higher than in scenarios a & b above. This
scenario also offers the lowest barrier to increases in landfill
disposal costs.
33. The outcome of the
table 4.0 above is also shown graphically as Appendix 3.
Legal Implications (to Include Human Rights Implications)
34. Given the potential
scope of the procurement, its potential value and complexity, it is
proposed that the Competitive Dialogue procedure is used with the
procurement carried out in accordance with the EU Public Sector
Procurement Directive (2004/18/EC). The competitive dialogue
process has advantages in that it enables the authorities to enter
into dialogue with bidders as to the solutions available to meet
their requirements, and disadvantages in that it is a resource
intensive process that is costly to both the authorities and
bidders.
35. The proposed
procurement is based on an overall output requirement to deal with
35% of the authorities’ residual waste, reflecting the expected
requirements of the authorities presuming compliance with landfill
diversion targets that are expected to be set. However,
changes in law/policy on a European or national level (re treatment
and disposal of residual waste/limitation on energy from waste
levels), and/or changes in the amounts and composition of residual
waste produced, could have a significant impact on any proposed
procurement, the viability of any solutions proffered and the costs
involved.
36. When two or more
local authorities decide to work together to achieve an objective,
such as procuring a residual waste treatment facility, it is
necessary to put in place 'Governance Arrangements' that enable
decisions to be made on behalf of the authorities to ensure the
timely progression and management of the Project. The
Partnership proposes to structure its governance arrangements on
the basis of a Joint Committee with a Lead Authority. These
arrangements are established pursuant to the powers in section 101
of the Local Government Act 1972. They would be enshrined in
an inter authority Joint Working Agreement (JWA1), which would
define the parties’ responsibilities and obligations during the
procurement process.
37. Once resolved to
commence the procurement and conclude the JWA 1 the authority is,
to a significant degree, locked into the process. Whilst the
ultimate decision to award the contract will be reserved to each
authority, the effect of concluding the JWA1 is that if the
procurement process results in solution that put simply, is within
the affordability envelope, meets the requirements and criteria set
(and is shown to do so when the final business case is produced)
then the expectation will be that a contract is awarded. In
such a scenario, should any partnering local authority determine
not to award a contract (in other words withdraw) then that
authority is likely to face significant financial consequences.
Similarly if any authority determines to withdraw from the
procurement process, once commenced, then such authority is likely
to face significant financial consequences. It should be
noted that damages will be assessed at the time of withdrawal/
decision not to proceed and that the agreement contains provision
whereby the damages payable by any one local authority will be
capped at £3,000,000. Accordingly, the decision to approve
the affordability envelope, conclude the JWA1 and commence the
procurement is a significant decision for each authority and will
impact on future budget commitments. For this reason the ultimate
decision must be taken by full Council. It is for this reason
so much effort has gone into the preparation of the Approved OBC,
pre procurement preparatory work, the OBC Health-check in
considering affordability and the other issues raised.
Crime and Disorder Implications
38. There are no crime
and disorder implications.
Equal Opportunities Implications (to include Welsh Language
issues)
39. There are no Equal
Opportunity implications.
Corporate/Service Objectives
40. Enhancing the
environment to ensure that people living, visiting and working in
the Vale have access to a clean and high quality local
environment.
Service targets:
· Increase the
percentage of total waste arising that is recycled from 25.54% in
2005 to 35% by 2009;
· Reduce the
percentage of total waste arising that is disposed of in landfill
sites from 70.8% in 2005 to 65% by 2009;
· Service
Action;
· E9 Facilitate a
regional solution to waste disposal through the Connecting South
East Wales initiative (2007).
Policy Framework and Budget
41. This report is a
matter for decision by Full Council.
Consultation (including Ward Member Consultation)
42. None.
Background Papers
· Approved Outline
Business Case for Prosiect Gwyrdd (redacted version) Autumn
2008
· Initial Site
Assessment Parsons Brinkerhoff September 2008
· Council Corporate
Plan (2006-10)
· WAG “Future
Directions” Policy Paper – April 2009
· WAG Revised Waste
Strategy for Wales Consultation Document April 2009.
Contact Officer
Clifford Parish, Operational Manager Waste
Management and Cleansing Tel No: 029 20673220
Officers Consulted
Accountant, Building and Vehicle Services
Operational Manager Legal Services
Head of Planning and Transportation
Responsible Officer:
Rob Quick, Director of Environmental and
Economic Regeneration
APPENDIX INDEX
The following Appendices are attached to this
report:-
|
Appendix
1
|
Prosiect Gwyrdd Common Report 2
|
|
|
Appendix 1
|
Appendix
'A':
|
A Recommendation in Cabinet Report dated 17th
December, 2009
|
|
*Appendix 1
|
Appendix
'B':
|
OBC Health Check 2009 Addendum - Redacted
|
|
*Appendix 1
|
Appendix
'C':
|
Site Evaluation Report - Redacted
|
|
*Appendix 1
|
Appendix
'D'
|
JWA1 - Redacted
|
|
Appendix 1
|
Appendix
F
|
Partnership Affordability Model (graph)
|
|
Appendix 1
|
Appendix
G
|
Affordability Envelope VOG - redacted
|
|
Appendix
2
|
VOG Affordability Model (graph)
|
|
|
Appendix
3
|
Whole System Costing VOG 100% waste (Graph)
|
|
|
Appendix
4
|
Prosiect Gwyrdd Funding Offer Letter - 15th May
2009
|
Tabled at meeting
|
*Redacted copies of these documents are available in the
Members room.
|