We use cookies for website functionality and to help analyse our traffic so we can improve our services. Necessary cookies help make the website usable by enabling basic functions like page navigation, the website cannot function properly without these cookies. Please choose your preferences below. Cookie Information
Allow all Cookies Allow selection
Wednesday, 10 July 2019
Vale of Glamorgan
After Welsh Government opted not to commit any more money to the work, this investment will ensure the Welsh Transport Appraisal Guidance (WelTAG) Stage 2 study is concluded.
Contractors Arcadis Consulting Ltd have been selected to carry out the work and it is anticipated the public will be consulted on its outcomes early next year.
These could include improvements to active travel and public transport as well as the possibility of a bypass for the village.
“It is important that this latest stage of work to explore potential travel improvements for Dinas Powys is completed so we can accurately plot the best way forward. “To that end, the Council has decided to provide the remaining funding for the WelTAG Stage 2 study and this work will commence in the near future. Afterwards, the conclusions will be thoroughly considered, along with opinions of all interested parties, before any decisions on what follows are taken.” - Cllr Peter King, Vale of Glamorgan Council Cabinet Member for Neighbourhood Services and Transport.
“It is important that this latest stage of work to explore potential travel improvements for Dinas Powys is completed so we can accurately plot the best way forward.
“To that end, the Council has decided to provide the remaining funding for the WelTAG Stage 2 study and this work will commence in the near future. Afterwards, the conclusions will be thoroughly considered, along with opinions of all interested parties, before any decisions on what follows are taken.” - Cllr Peter King, Vale of Glamorgan Council Cabinet Member for Neighbourhood Services and Transport.
Specifically, the work will involve:
Engaging with Network Rail to understand the constraints and potential costs associated with constructing a bypass and junction in the vicinity of the existing railway tunnel.
Undertaking concept design, modelling and costing of suggested improvements to the Merrie Harrier junction to improve capacity. These will be considered in the context of costs associated with the pink and green route options.
Commissioning Transport for Wales to carry out strategic modelling using the South East Wales Transport Model of the bypass proposals.
Updating the economic appraisal for the green/pink route alignment and updating the transport case along with the Stage 2 report.
Undertaking public consultation on the findings of the Stage 2 report, finalising it and making recommendations to be taken forward to the WelTAG Stage 3 Full Business Case.